Update: Greece’s Alexandroupolis FSRU to receive first LNG cargo on Friday

Gastrade’s FSRU-based LNG import terminal off Greece’s Alexandroupolis will receive its first cargo of liquefied natural gas on Friday.

“GasLog Hong Kong is indeed scheduled to arrive at Alexandroupolis on Friday, February 16 bearing the commissioning cargo for the Alexandroupolis FSRU,” a spokeswoman for Gastrade confirmed to LNG Prime on Wednesday.

“We will provide further information once STS operations have commenced,” she said.

LNG Prime reported on Tuesday that the 2018-built 174,000-cbm LNG carrier, GasLog Hong Kong, is expected to arrive at the 153,600-cbm Alexandroupolis late on February 15, its AIS data provided by VesselsValue showed.

The LNG carrier, chartered by France’s TotalEnergies, previously picked up a cargo at Sempra’s Cameron LNG plant in Louisiana.

TotalEnergies is a shareholder in Cameron LNG which has a capacity of about 12 mtpa of LNG.

Last month, Gastrade said that the arrival of the commissioning cargo at its FSRU-based LNG import terminal off Alexandroupolis had been postponed due to bad weather.

The firm previously expected to receive the commissioning cargo on January 20.

Greece’s first FSRU

Gatsrade’s shareholders include founder Copelouzou, DESFA, DEPA, Bulgartransgaz, and GasLog.

Shareholder and Greek LNG shipping firm GasLog told Singapore’s Keppel Offshore & Marine, now Seatrium, in February 2022 to proceed with the conversion of the 2010-built, GasLog Chelsea, to an FSRU.

Seatrium’s yard in Singapore completed the conversion work on the 153,600-cbm Alexandroupolis in November last year.

Greece’s first FSRU arrived in Alexandroupolis from Singapore on December 17 and mooring hook-up was completed on December 23, 2023.

The FSRU is located in the sea of Thrace at a distance of 17.6 km SW from the port of Alexandroupolis and 10 km from the nearest coast of Makri. Also, it is connected to a high-pressure subsea and onshore gas transmission pipeline.

Once operational, the pipeline will deliver natural gas to the Greek transmission system and onwards to the final consumers in Greece, Bulgaria, Romania, North Macedonia, Serbia and further to Moldova and Ukraine to the East and Hungary and Slovakia to the West, Gastrade said.

The Alexandroupolis LNG terminal will have a capacity of 5.5 Bcm.

With this project, Greece will get its first FSRU and the second LNG import facility, adding to DESFA’s import terminal located on the island of Revithoussa.

In addition to this unit, Gastrade is also planning to install a second FSRU offshore Alexandroupolis.

(Article updated on Wednesday, February 14 to include a comment by a Gastrade spokeswoman.)

Most Popular

Glenfarne’s Texas LNG seeks DOE extension

US energy firm Glenfarne is seeking an extension from the US Department of Energy to extend the non-FTA export start deadline for its planned 4 mtpa Texas LNG export terminal in the port of Brownsville.

Petrovietnam units plan new LNG-to-power project

PV Power and PV Gas, units of state-owned Petrovietnam, signed cooperation agreements to secure gas supplies for power plants in southwestern Vietnam and explore developing an integrated liquefied natural gas (LNG) project in the northern port city of Hai Phong.

China’s GCL inks deal for second phase of Ogaden LNG project in Ethiopia

China’s GCL has signed an agreement with China Jurong Group to advance the second phase of its Ogaden LNG project in Ethiopia’s Somali region.

More News Like This

Greek LNG imports climb in January-September

LNG deliveries to DESFA’s Revithoussa LNG terminal and Gastrade’s Alexandroupolis FSRU-based facility in Greece rose in January-September this year, with the US supplying the majority of the volumes.

TotalEnergies expects Q3 LNG results to rise sharply

French energy giant TotalEnergies, one of the world’s largest LNG players, expects its integrated LNG results to rise sharply in the third quarter compared to the prior quarter, driven by higher prices.

Gastrade chairman Theodore Panagos dies

Greece’s Gastrade, the operator of the Alexandroupolis FSRU-based LNG import terminal, said that its chairman, Theodore Panagos, passed away.

TotalEnergies plans second Mozambique LNG phase

French energy giant TotalEnergies plans to expand its Mozambique LNG project, currently under construction in Cabo Delgado province, with a second phase, according to management.