Chevron to restart first Gorgon LNG train in March

Chevron plans to complete repair works on heat exchangers at the first Gorgon LNG train in Australia in March this year after it will shut down the facility’s third unit for inspections.

The US energy giant said last month it was repairing heat exchangers at the first train after finding similar issues that closed the plant’s second production unit.

To remind, Chevron brought back online the second train at its 15.6 mtpa LNG facility on Barrow Island in November following months of repairs related to “weld quality issues” in propane heat exchangers.

Chevron’s finance chief Pierre Breber told analysts on Friday during the company’s fourth-quarter earnings call that “Gorgon Train 1 repairs are nearing completion and we expect the facility to be back online in March.”

“After Train 1 is back online, Train 3 will be taken out of service for the propane vessel inspections, any repairs and the planned turnaround,” he said.

Chevron reported a full-year 2020 loss of $5.5 billion compared with earnings of $2.9 billion in 2019. The firm also posted a loss of $665 million for the fourth quarter, compared with a loss of $6.6 billion last year mainly related to the Covid-19 pandemic.

Wheatstone repairs to cut Q1 LNG production

Besides Gorgon, Chevron is also conducting repairs at its second giant LNG project in Australia, Wheatstone.

The project includes two LNG trains with a combined capacity of 8.9 million metric tons per annum and a domestic gas plant.

“At Wheatstone, production is modestly below capacity while we repair an inlet separator. We do not expect production impacts in the second quarter,” Breber said during the call.

Chevron CEO Michael Wirth said that Wheatstone should be back up to full capacity until a turnaround that begins late third quarter and runs into fourth.

Together with the Gorgon repairs, Chevron will have a “lighter” Australia production this year but a big part of that includes “planned turnaround activity and then there’s an increment related to these repairs,” Wirth said.

In addition, Wirth also said that Gorgon repairs did not affect the firm to provide LNG to customers under its contractual commitments in the fourth quarter.

Most Popular

NFE logs $557 million net loss, continues Puerto Rico supply deal talks

US LNG player New Fortress Energy reported a net loss of $557 million in the second quarter of 2025, while it continues to negotiate a long-term gas sale agreement with PREPA to provide gas island-wide in Puerto Rico.

MOL gets OK for two LNG carrier designs with sails

Japan’s shipping giant MOL has secured approval from classification society Lloyd's Register (LR) for two liquefied natural gas (LNG) carrier designs equipped with four Wind Challenger sails.

Jera in Montenegro LNG terminal move

Japan's power firm and LNG trader Jera and the government of Montenegro plan to sign a memorandum of understanding on the development of a liquefied natural gas (LNG) terminal and an associated gas-fired power plant.

More News Like This

Seatrium upgrades Chevron’s LNG tanker

Singapore’s Seatrium has completed upgrading Chevron’s last LNG carrier as part of a project aimed at slashing emissions.

Chevron, China’s ENN seal second LNG SPA

US energy giant Chevron has signed a second LNG sales and purchase agreement with Chinese independent gas distributor ENN.

Energy Transfer, Chevron expand Lake Charles LNG deal

Energy Transfer, the developer of the proposed Lake Charles LNG export facility in Louisiana, has signed a new deal with energy giant Chevron for additional LNG volumes.

Chevron: Wheatstone LNG ships 1000th cargo

The Chevron-operated Wheatstone LNG plant in Western Australia has shipped its 1000th cargo of liquefied natural gas since 2017.