Kosmos: FPSO on its way to GTA site

The floating production, storage, and offloading (FPSO) unit which will serve the BP-operated Greater Tortue Ahmeyim FLNG project has left Tenerife and is on its way to the GTA project site off the coasts of Mauritania and Senegal, according to project partner Kosmos Energy.

Kosmos said in its first quarter results report on Tuesday that “inspection and repair of the vessel’s fairleads is complete with the vessel now en route to the project site with mooring work to commence thereafter.”

“Hookup and commissioning of the FPSO remain on the critical path to first gas, expected in the third quarter of 2024 with first LNG expected in the fourth quarter of 2024,” Kosmos said.

According to is AIS data, the FPSO left Tenerife on May 5 and is expected to arrive at the GTA site later this week.

Kosmos confirmed in its 2023 results report in February the delay in the project’s commissioning saying that first LNG is expected in the fourth quarter of this year.

The project’s FPSO unit left Cosco Shipping Heavy Industry’s yard in Qidong, China in January last year.

With eight processing and production modules, the FPSO will process around 500 million standard cubic feet of gas per day.

The gas supplies will then be transported by pipeline to the FLNG unit at the GTA hub where it will be cryogenically cooled in the vessel’s four liquefaction trains and stored before transfer to LNG carriers.

Kosmos FPSO on its way to GTA site
Golar LNG’s converted FLNG, Gimi (Image: BP)

FLNG

Golar LNG’s FLNG Gimi, which was converted from a 1975-built Moss LNG carrier with a storage capacity of 125,000 cbm, departed Seatrium’s yard in Singapore on November 19.

Golar announced in January the arrival of the 2.5 mtpa FLNG at the site. However, Golar and BP agreed that the FLNG “will proceed to moor offshore Tenerife while awaiting completion of the necessary preparatory activities,” Golar said at the time.

BP said in February that Gimi arrived at the site of the GTA project.

The unit is at the heart of the GTA Phase 1 development, operated by BP with partners, Kosmos, PETROSEN, and SMH.

Kosmos said in the update that the partnership is continuing to work with Golar to accelerate commissioning work of the unit.

Moreover, the subsea workscope is “progressing in line with expectations with the flowline installation now complete and final connection work ongoing,” Kosmos said.

In October last year, BP selected Swiss-based offshore contractor Allseas to complete the remaining subsea pipelay scope for the FLNG project, replacing previous contractor Houston-based McDermott.

Allseas said in February it has completed the infield pipelay scope for the project.

Most Popular

Atlantic LNG shipping rates, European prices down

Atlantic LNG freight shipping rates and European prices decreased this week compared to the week before.

Glenfarne becomes majority owner of Alaska LNG

US energy firm Glenfarne has signed definitive agreements with state-owned Alaska Gasline Development Corporation to become the majority owner of the giant Alaska LNG export project.

Petronas to supply LNG to PetroVietnam Gas

Malaysian energy giant Petronas will supply liquefied natural gas (LNG) to PetroVietnam Gas, a unit of state-owned PetroVietnam, next month. The two firms will also look into the possibility of signing long-term LNG contracts.

More News Like This

BP takes FID on Ginger gas project in Trinidad and Tobago

UK-based energy giant BP has taken the final investment decision on the Ginger gas development offshore Trinidad and Tobago.

Argentina’s Enarsa gets offers for LNG cargo tender

Argentina's state-owned LNG importer Energia Argentina (Enarsa) has received seven offers for its first LNG cargo tender in 2025.

Shell CEO expects progress on Venture Global arbitration this year

Shell’s CEO Wael Sawan expects to have an update on an arbitration dispute with US LNG exporter Venture Global LNG later this year.

Golar seals $1.2 billion leasing deal for FLNG Gimi

Floating LNG player Golar LNG has entered into lease agreements with a consortium of Chinese leasing companies for the refinancing of the existing FLNG Gimi debt facility.