NFE plans to launch Altamira LNG production in May

US LNG firm New Fortress Energy expects to start production of liquefied natural gas at its first FLNG project off Altamira, Mexico in May.

The Wes Edens-led firm said in its first-quarter results report on Wednesday that the project is in final stages of commissioning.

According to the firm, first LNG is expected later this month and first full cargo is expected in June.

NFE’s first 1.4 mtpa FLNG asset located offshore Altamira has reached mechanical completion in January this year.

The company said in its fourth-quarter report in February this year it was expecting first LNG in March and first cargo in April 2024.

NFE sent its liquefaction rig Pioneer II on September 26, 2023 to Altamira to start serving the FLNG project.

Prior to this, NFE’s utilities and accommodation rig, Pioneer III, arrived off Altamira, as well as the gas treatment rig.

The FLNG project consists of three rigs, Pioneer I, II, and III.

Besides the three rigs, the 160,000-cbm Penguin FSU serves the project as a floating storage unit.

Expected value exceeds $3 billion

Chris Guinta, NFE’s finance chief, said during the earnings call later on Wednesday that the expected value of its first FLNG unit exceeds $3 billion.

This value is driven by two components, including the cost to replicate the liquefier and time value of having production in today’s “elevated” global LNG market.

The replacement cost at $1,400 per tonne has a value of about $2 billion and value of “in the money” LNG for about four years is worth about $1 billion.

NFE expects the unit to produce a bit more than 90 LNG cargoes in the next four years.

The firm said the next step following COD is financing, and the goal is to finance the asset in secured financing.

“We are targeting $1.5 billion to $1.75 billion in proceeds which represents a low loan to value given the asset exceeds $3 billion,” Guinta said.

Incident

NFE recently said that “a minor technical issue” which took place last month on one of its rigs as part of the Altamira LNG project will not affect the launch of production.

The incident took place on Pioneer II during the commissioning of the cold box.

Guinta said during the earnings call that the “incident with a pipe fracture inside our cold box” took place last Friday, April 26.

“This was extremely unfortunate given we were expecting LNG a mere 72 hours later,” he said.

“The pipe incident caused the boxes insulation material, a non-toxic volcanic sand called perlite, to be admitted all over the rigs,” Guinta said.

“Thankfully, no significant injuries were sustained.. and no adjacent systems were damaged,” he said.

He said the damage was isolated to one pipe and manifold in the cold box, and is expected to be repaired by next weekend.

Results

NFE reported net income of $57 million in the first quarter of 2024, down compared to $151.6 million in the same quarter last year and $214.9 million in the prior quarter.

The company’s revenue rose to $690.3 million in the first quarter of this year compared to $579.1 million in the same quarter last year but it dropped compared to $758.4 million in the previous quarter.

Also, Adjusted Ebidta of $340 million dropped compared to $440 million in the first quarter last year and from $387.6 million in the prior quarter.

NFE’s board of directors approved a dividend of $0.10 per share.

Most Popular

Adnoc launches LNG marketing and trading platform

UAE's energy giant Adnoc has launched a global liquefied natural gas (LNG) marketing and trading platform, targeting 47 million tonnes per annum (mtpa) of combined marketable LNG by 2035.

Kiewit gets limited notice to proceed for Glenfarne’s Texas LNG

US construction and engineering firm Kiewit has received a limited notice to proceed from Glenfarne's Texas LNG for the latter's planned 4 mtpa LNG export terminal in the port of Brownsville.

Glenfarne’s commodities unit, BGN ink preliminary LNG supply deal

Glenfarne's unit Glenfarne Global Commodities has signed a heads of agreement with Switzerland-based energy trader BGN for the long-term supply of liquefied natural gas (LNG).

More News Like This

NFE says UK court approves restructuring plan

US LNG player New Fortress Energy said that a UK court approved its previously announced restructuring plan.

NFE gets strong support for $5.8 billion restructuring plan

US LNG player New Fortress Energy said it had received "strong indications" of support from its stakeholders for the previously announced $5.8 billion UK restructuring plan.

NFE seals long-term deal for Brazilian LNG terminal

US LNG firm New Fortress Energy said on Tuesday that its Brazil platform has signed a long-term lease and capacity agreement for the FSRU-based LNG import terminal in Santa Catarina, Brazil.

NFE inks restructuring support deal

US LNG player New Fortress Energy said it had entered into a restructuring support agreement with its creditors as part of a consensual UK restructuring plan, in what is expected to be one of the largest consensual UK RP restructuring transactions ever completed. NFE will also separate its Brazilian operations into an independent, standalone energy platform.