Excelerate’s FSRU to visit yard for repairs

Excelerate Energy’s 138,000-cbm FSRU Summit LNG, which serves Bangladesh’s second LNG import terminal located offshore Moheshkhali Island in the Bay of Bengal, will visit a yard for repairs after it was damaged last week during cyclone Remal.

“Due to the extent of the damage sustained by the FSRU Summit LNG, the vessel is expected to sail to a shipyard facility for repairs,” Excelerate told LNG Prime in an emailed statement late on Thursday.

“Excelerate is committed to making any necessary repairs and returning to service in Bangladesh as soon as possible,” the company said.

Exclelerate did not provide further information.

On May 27, 2024, at approximately 20:10 local time, the FSRU Summit LNG sustained damage during “adverse weather conditions” from a floating object which made several points of contact with the vessel’s starboard side.

Several reports said, citing a statement by Summit LNG, that “the impact sheared the vessel’s outer hull, approximately one meter below the waterline, leading to water ingress into the ballast tanks.”

Summit reportedly hopes to complete the repairs in either Singapore or the Middle East in three weeks.

LNG Prime previously invited Bangladesh’s Summit to comment on the matter, but we did not receive a response.

In August 2017, Summit entered into a 15-year charter agreement with Excelerate for the FSRU, and the unit began operations at the facility in April 2019.

The terminal has a sendout capacity of 500 million standard cubic feet per day (MMscf/d) of natural gas, and the FSRU is connected to shore by a six kilometers long subsea pipeline.

Excelerate’s FSRU also serves Bangladesh’s first LNG import facility, Moheshkhali Floating LNG or MLNG, operated by Petrobangla.

Launched in 2018, the 138,000-cbm FSRU Excellence completed its 100th STS transfer offshore Bangladesh in 2021.

Most Popular

CoolCo seeks long-term employment for two LNG carriers

In August, Coolco said it plans to employ its first newbuild LNG vessel, Kool Tiger, on a shorter deal...

BP, partners take FID on $7 billion Tangguh UCC project

BP said in a statement on Thursday the Tangguh Ubadari, CCUS, compression project (UCC) has the potential to unlock...

LNG Canada pipeline enters commercial service

Canada's TC Energy said on Tuesday CGL had executed a commercial agreement with LNG Canada and CGL customers that...

More News Like This

RPGCL seeks new spot LNG cargo

According to a tender document posted on RPGCL’s website, the delivery window is December 30-31, 2024. RPGCL issued the tender...

RPGCL launches new spot LNG cargo tender

According to a tender document posted on RPGCL’s website, RPGCL is seeking two cargoes for Delivery in December. The delivery...

Excelerate working on additional LNG deals, CEO says

Excelerate operates ten FSRUs, one of the world’s largest fleets of such vessels, and these units are located worldwide. In...

Excelerate inks mid-term LNG deals, plans FSRU conversions

Excelerate revealed these developments in its third-quarter results report. In the third quarter, Excelerate signed medium-term agreements for LNG purchases...