Boskalis completes LNG Canada dredging works

Dutch dredging and offshore contractor Boskalis said it has completed works at the Shell-led LNG Canada development in Kitimat after winning a contract back in 2018.

The firm started working under the contract worth more than 100 million euros ($121 million) in October 2018. It finalized the operations last week.

The dredging scope included the removal and remediation of contaminated and non-contaminated sediments at the site of the LNG facility in order to provide the required physical space and marine access.

“For three seasons, our colleagues worked under harsh weather conditions to remove and remediate soil at the site of the future terminal in Kitimat,” Boskalis said.

Boskalis completes LNG Canada dredging works
Image: Boskalis

In addition, the company’s hopper dredgers Beachway and Shoreway have left for Vancouver to further prepare for demobilization. Boskalis will also soon load its cutter dredger Edax and other floating equipment onto its semi-submersible heavy transport vessel Triumph.

The giant LNG Canada project includes the construction of 14 million tonnes per annum (mtpa) export capacity from the first two trains, with the potential to expand to four trains in the future.

Shell’s chief executive Ben van Beurden recently said the project was slightly behind with construction works due to disruptions caused by the Covid-19 pandemic but LNG Canada still expects first LNG shipment in the middle of the decade.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and Kogas of South Korea.

- Advertisements -

Most Popular

New LNG carrier joins Celsius fleet

South Korea’s Samsung Heavy Industries has hosted a naming ceremony for one 180,000-cbm LNG carrier it built for Denmark’s...

US LNG exports climb to 22 shipments

US liquefied natural gas (LNG) exports rose in the week ending April 24 compared to the week before, according...

China’s CNOOC nears launch of six giant Binhai LNG tanks

China National Offshore Oil Company (CNOOC) said it had completed the main construction on the six giant LNG storage...

More News Like This

Shell CEO: LNG Canada to start commissioning later this year

Shell’s LNG Canada terminal is more than 90 percent complete and the project is preparing to launch commissioning activities...

LNG Canada CEO: start-up activities will take more than a year to complete

Shell's LNG Canada project is now preparing to launch start-up activities next year and this program will take more...

HaiSea Marine takes delivery of its first LNG-powered tug

Turkey’s Sanmar has delivered the first of two LNG-powered tugs to Canada's HaiSea Marine, a joint venture majority owned...

Third LNG Canada electric tug delivered

HaiSea Marine’s third and final electric tugboat which will serve the Shell-led LNG Canada project is on its way...