Shell doesn’t expect Prelude FLNG restart before Q3

LNG giant Shell is not expecting to restart production at its Prelude FLNG facility offshore Western Australia before July.

Shell hasn’t exported any cargoes from the FLNG for almost five months following an electrical trip on February 2.

“Start-up timing will depend on Covid-19 constraints and compliance with government directions”, a Shell spokesperson said in a emailed statement on Monday.

This will result in a reduction in the number of people on board the FLNG facility.

The spokesperson said that due to these constraints and the impact on the start-up processes, “production is not expected before the third quarter”.

Prelude shipped its first cargo last year after several start-up delays.

The FLNG has the capacity to produce 3.6 mtpa of LNG, 1.3 mtpa of condensate and 0.4 mtpa of LPG.

Shell operates the Prelude FLNG, located 475 km from Broome in Western Australia, with a 67.5 per cent stake.

Japan’s Inpex holds a 17.5 per cent stake, Korea’s Kogas 10 percent, while Taiwan’s CPC holds 5 per cent.

New Prelude FLNG chief

In a related development, Shell’s Australian unit has appointed a new executive to lead the world’s largest FLNG project.

Stacey Orlandi is taking over as VP Prelude from Rob Jager who is leaving the FLNG project and Shell.

Rob will be retiring from Shell after 42 years with the LNG giant to focus on “other non-executive roles”.

“We thank Rob Jager for his service in the role, during which time he oversaw significant progress from the facility start-up phase, including achieving first cargo in June 2019”, the spokesperson said.

Orlandi, based in the Netherlands, is currently Shell’s vice president asset management excellence for integrated gas and new energies.

“Stacey will be immediately engaged in a transition period over the coming weeks”, the spokesperson said.

The spokesperson added that “her physical relocation will depend on Covid-19 travel restrictions”.

Most Popular

Venture Global, Petronas seal 20-year LNG SPA

US LNG exporter Venture Global LNG has signed a 20-year LNG supply contract with Malaysian energy giant Petronas for volumes from the CP2 project in Louisiana.

Golden Pass LNG seeks re-export approval

Golden Pass LNG, a joint venture owned by energy giants QatarEnergy and ExxonMobil, is seeking approval from the US DOE to export previously imported LNG from October, as it nears the launch of the first liquefaction train.

Delfin inks new deals for US FLNG project, eyes FID later this year

Delfin Midstream, the US developer of a floating LNG export project offshore Louisiana, is moving forward with the project by signing new deals with Siemens Energy, Samsung Heavy, and Black & Veatch.

More News Like This

Shell’s LNG Canada to ship second cargo

Shell-led LNG Canada is expected to soon ship the second cargo of liquefied natural gas from the Kitimat facility on the west coast of Canada, according to shipping data.

Shell ships first LNG Canada cargo

LNG giant Shell and its partners have shipped the first cargo produced at the LNG Canada facility in Kitimat, on the west coast of Canada.

Peru LNG shipped five cargoes in June

Peru LNG’s liquefaction plant at Pampa Melchorita has shipped five liquefied natural gas cargoes in June, the same as in the previous month.

Knutsen, Shell name ninth LNG newbuild

Norwegian shipowner Knutsen and UK-based energy giant Shell have named the ninth and final LNG carrier in a series of 174,000-cbm vessels.