Coral Sul FLNG gets 1st topside module

South Korea’s Samsung Heavy Industries has lifted the first topside module onboard the Coral Sul FLNG that will be used for a project offshore Mozambique.

With the lifting of the power generation module, the FLNG project led by Italy’s Eni marks the beginning of the integration between the hull and the topside, according to a Coral FLNG statement on Tuesday.

Samsung Heavy is also building the hull and the shipyard launched it in the beginning of January.

The massive topside includes 12 process modules weighing around 70,000 tons.

“The on-time achievement of such a significant milestone is even more relevant now considering the ongoing challenges caused by the Covid-19 pandemic,” the statement said.

“The construction of the FLNG facility is progressing well aiming towards the commencement of production in 2022,” it said.

Coral FLNG
Image: Coral FLNG

432 metres long and 66 metres wide

The FLNG unit is part of the Coral South project. The development will produce 450 bcm of gas from the giant Coral reservoir in the Area 4 block offshore Mozambique.

Mozambique Rovuma venture, consisting of Eni, ExxonMobil and CNPC, is the operator of Area 4.

The venture holds a 70 percent stake in the Area 4 exploration and production concession contract.

In addition, Galp, Kogas and Empresa Nacional de Hidrocarbonetos each hold a 10 percent interest in Area 4.

Eni is leading the construction and operation of the FLNG unit on behalf of the partnership.

The FLNG facility will have a liquefaction capacity of 3.4 million tonnes per year.

The unit will be 432 metres long and 66 metres wide and weigh about 220,000 tons.

Furthermore, it will be able to house up to 350 people in its eight-storey accommodation module.

Construction works on the Coral Sul FLNG started in 2018 and are ongoing in seven operational centres across the world.

- Advertisements -

Most Popular

Sempra updates on Port Arthur LNG work

US LNG exporter Sempra and compatriot engineering and construction firm Bechtel are moving forward with construction on the first...

Deutsche ReGas: FSRU leaves Lubmin to start Mukran job

The 2009-built 145,000-cbm, FSRU Neptune, has left Germany's industrial port of Lubmin and is expected to arrive in Mukran...

Germany’s DET to launch second Wilhelmshaven FSRU terminal in H2 2024

State-owned German LNG terminal operator DET expects to launch its second FSRU-based LNG import terminal in Wilhelmshaven in the...

More News Like This

Eni’s Mozambique FLNG hits production milestone

US-based Air Products said its dual mixed refrigerant LNG process technology and equipment, which has been deployed at Eni's...

CMA CGM’s LNG-powered containership named in South Korea

South Korea's Samsung Heavy Industries has hosted a naming ceremony at its yard in Geoje for CMA CGM's LNG-powered...

New LNG carrier joins Celsius fleet

South Korea’s Samsung Heavy Industries has hosted a naming ceremony for one 180,000-cbm LNG carrier it built for Denmark’s...

Eni expects ‘some’ LNG cargoes from Egypt next winter

Italian energy firm Eni expects to export "some" liquefied natural gas cargoes from the Damietta terminal in Egypt next...