Cheniere still expects to launch sixth Sabine Pass train this year

US LNG exporter Cheniere still expects to launch the sixth production train at its Sabine Pass plant in Louisiana by the end of this year. The firm also sees substantial completion of the unit about a year before than planned.

The 25 mtpa Sabine Pass plant has five operational trains and is currently the largest such facility in the US.

Bechtel is building the sixth train which will add 5 mtpa of capacity to the facility. In total, this is the ninth train the engineering giant is building for Cheniere, including the Corpus Christi plant where Bechtel recently handed over the third train.

Cheniere said in its first-quarter report it now expects substantial completion of Train 6 in the first half of 2022.

This means that the firm now expects Bechtel to complete the train one year ahead of the original schedule as it previously also moved the estimate from the first half of 2023 to the second half of 2022.

Commissioning to start this year

“I’d like to say, we have figured out how to stick build these trains faster and better than probably anywhere else in the world. And it is way ahead of accelerated schedule probably close to a year ahead,” Cheniere’s chief executive Jack Fusco told analysts during the company’s quarterly earnings call on Tuesday.

“So I would expect that barring decent weather because we are about ready to head into the hurricane season again, which seems almost never-ending anymore. But baring decent weather, we’ll be producing LNG and commissioning on that train before the end of the year,” he said.

Fusco said earlier this year the company had expected to launch the sixth train this year.

In the first quarter, Cheniere’s revenue increased to $3.09 billion from $2.71 billion a year earlier.

Consolidated adjusted Ebitda rose 40 percent to $1.45 billion primarily due to increased margins while net income increased 5 percent to $393 million, Cheniere has said.

Most Popular

QatarEnergy CEO says damaged Ras Laffan LNG trains to take three years to repair

State-owned LNG giant QatarEnergy expects the damage to two liquefaction trains at its giant Ras Laffan complex to take three years to repair, according to Qatar’s energy minister and CEO of QatarEnergy, Saad Sherida Al-Kaabi.

Hanwha Ocean, KR to develop LNG bunkering vessel concepts

South Korean shipbuilder Hanwha Ocean is teaming up with Korean Register (KR) to jointly develop two design concepts for an 18,000-cbm LNG bunkering vessel.

Maersk orders 26 LNG-powered container vessels

Danish shipping giant Maersk has ordered 26 LNG dual-fuel container vessels as it continues to expand its dual-fuel fleet.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project more than 50 percent complete

Cheniere's Corpus Christi Midscale Trains 8 and 9 project in Texas is more than 50 percent complete, according to the latest construction update.

Equinor takes first LNG cargo from Cheniere

Norwegian energy firm Equinor has taken delivery of its first liquefied natural gas (LNG) cargo under long-term supply agreements with US LNG exporting giant Cheniere.

Cheniere completes CCL Stage 3 project

US LNG exporter Cheniere has completed the Corpus Christi Liquefaction Stage 3 expansion project in Texas. In addition, Cheniere has also exported its 5,000th LNG cargo since 2016.

Germany’s BASF gets first LNG cargo under Cheniere contract

German chemicals giant BASF has received its first liquefied natural gas (LNG) cargo under a long-term contract with US LNG exporter Cheniere.