Norway’s Equinor wraps up internal investigation into Hammerfest LNG fire

Norway’s Equinor has completed its internal investigation into a fire that broke out at the Hammerfest LNG plant in September last year.

To remind, Equinor closed the Hammerfest LNG plant on September 28 following the fire in turbine 4. The plant will remain closed until March next year due to the scope of the repairs needed to restore the facility to safe production.

The completion of the company’s investigation also follows PSA’s recent announcement saying it has identified regulation breaches following its investigation into the fire.

Equinor said on Wednesday that the cause of the fire was “spontaneous ignition in the filters in the turbine’s air inlets, caused by excessively high temperature over a long period of time.”

“The anti-icing heat exchanger in the air inlet was used outside of its intended area of application, thus causing the high temperature that triggered the fire,” the firm said.

Contrary to PSA’s findings, Equinor said that its investigation group does not “believe that the maintenance interval for exchanging the filters that self-ignited is a contributing cause.”

However, both the PSA report and Equinor’s investigation confirm that the fire was unlikely to spread to other parts of the facility, it said.

“Several direct and underlying factors”

Equinor says a single technical or human error did not cause the incident. It was the result of “several direct and underlying factors.”

The investigation has considered underlying causes related to organisation, capacity, competence and management.

Equinor said it would follow up on the findings in a “dedicated improvement initiative.”

The Norwegian energy giant is also following up all the orders and nonconformities in the PSA’s investigation of the fire, and will present a plan to the PSA for complying with the orders by June 1.

Hammerfest LNG liquefies natural gas coming from the Snohvit field in the Barents Sea.

Gas reaches Hammerfest LNG via a 160-kilometer gas pipeline which became operational in the autumn of 2007.

The fuel produced at the facility mainly lands at LNG terminals in Europe but also in Asia.

Equinor is the operator of both the Snohvit field and Hammerfest LNG with a 36.8 percent stake.

Most Popular

McDermott bags Monkey Island LNG gig

Houston-based McDermott has secured a contract from Monkey Island LNG for its planned natural gas liquefaction facility in Cameron Parish, Louisiana.

Gazprom supplying gas from Kaliningrad FSRU

Gas giant Gazprom has completed tests at its 174,000-cbm FSRU Marshal Vasilevskiy off Russia's Kaliningrad, located between Lithuania and Poland. The firm said...

GTT develops new LNG fuel tank

French LNG containment giant GTT has developed a new cubic-shaped LNG fuel tank for commercial vessels, with a particular focus on LNG-fueled container vessels.

More News Like This

Cheniere clinches Botas LNG supply deal

Turkiye’s state-owned natural gas and LNG firm Botas has signed a deal to buy liquefied natural gas from US LNG exporting giant Cheniere. Botas also signed deals with SEFE, Equinor, and jera.

Equinor eyes LNG carrier order

Norwegian energy firm Equinor is interested in booking liquefied natural gas (LNG) carriers at yards in South Korea and China, according to shipbuilding sources.

Deutsche ReGas: BASF, Equinor book Mukran regas capacity

German chemicals giant BASF and Norwegian energy firm Equinor have booked long-term regasification capacity at the Deutsche ReGas-operated FSRU-based LNG import facility in Mukran, Germany.

Equinor resumes Hammerfest LNG ops

Norway’s Equinor has restarted its 4.3 mtpa Hammerfest LNG export plant following an unplanned shutdown over the weekend.