Video: main heat exchanger lands at LNG Canada site

Construction on the Shell-led LNG Canada export project in Kitimat continues to progress despite disruptions caused by the Covid-19 pandemic.

Three towering pieces of equipment critical to the gas liquefaction process have recently arrived at the site in Kitimat, as part of the project’s “going vertical” stage, LNG Canada said in a update.

LNG Canada crews spent the week of June 7th carefully offloading a 345-tonne main cryogenic heat exchanger and two precooler units, which weigh 308 tonnes and 284 tonnes respectively, it said.

The equipment arrived on board a cargo ship that docked at the LNG Canada project’s new material offloading facility (MOF) in Kitimat Harbour.

Moreover, crews then placed the equipment on large, self-propelled modular transporters, which would slowly move the pieces along the project site’s new three-kilometre-long haul road to the main construction area, LNG Canada said.

The largest of the three new pieces of equipment, the heat exchanger is approximately 50 metres in length. Once installed vertically, it will be among the most visible components at the LNG Canada facility.

In addition, this is the first of two units Linde built for the LNG Canada project while the second heat exchanger should arrive later this year, along with two more precoolers, LNG Canada said.

“Significant milestone”

“Taking delivery of our first main cryogenic heat exchanger and precoolers is another significant milestone for the LNG Canada project, and represents a number of firsts for us,” said LNG Canada CEO Peter Zebedee.

“It’s our first opportunity to receive critical infrastructure at our new material offloading facility, and our first heavy equipment transport along our new haul road to our main construction site,” Zebedee said.

To remind, Shell’s CEO Ben van Beurden said earlier this year that LNG Canada was slightly behind with construction works due to disruptions caused by the Covid-19 pandemic.

The CEO did not provide any additional information regarding the delays, but LNG Canada said last year these would not affect the first LNG shipment expected in the middle of the decade.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation and South Korea’s Kogas.

The giant project, worth more than $30 billion, includes the construction of 14 million tonnes per annum (mtpa) export capacity from the first two trains, with the potential to expand to four trains in the future.

Most Popular

Venture Global’s CP2 LNG to start mobilization and site preparation

Venture Global LNG's CP2 LNG has received approval from the US FERC to start mobilization and other limited activities for the LNG project in Louisiana.

Prime Infra to buy 60 percent stake in First Gen’s Batangas LNG terminal

First Gen has entered into a deal with Prime Infrastructure Capital under which the latter will acquire a 60 percent equity stake in First Gen's gas business in the Philippines, including the Batanagas LNG terminal.

Atlantic LNG shipping rates continue to decrease

Atlantic LNG freight shipping rates continued to decrease this week, while European prices also dropped compared to last week.

More News Like This

Shell shareholders re-elect CEO Wael Sawan

Wael Sawan will continue to lead London-based LNG giant Shell following shareholder voting at the company's annual general meeting on Tuesday.

Singapore’s FueLNG wraps up 400th STS bunkering operation

Singapore’s FueLNG, a joint venture consisting of Shell and Seatrium, has completed its 400th ship-to-ship (STS) LNG bunkering operation. FuelLNG delivered LNG to BYD Shenzen, which is said to be the world’s largest LNG-fueled car carrier.

Peru LNG terminal shipped three cargoes in April

Peru LNG’s liquefaction plant at Pampa Melchorita has shipped three liquefied natural gas cargoes in April due to restrictions on the transportation system, according to operator Hunt Oil.

CFO: Shell on track to ship first LNG Canada cargo in middle of 2025

LNG giant Shell remains on track to deliver the first liquefied natural gas cargo from its LNG Canada export terminal in Kitimat in the middle of this year, according to Shell's finance chief, Sinead Gorman.