Cheniere nears launch of sixth Sabine Pass train

US LNG exporter Cheniere is getting closer to the launch of the sixth production train at its Sabine Pass plant in Louisiana.

The Federal Energy Regulatory Commission (FERC) said in a letter dated June 29 it had approved Cheniere’s request to introduce gas and commission the Train 6 fuel gas system.

Cheniere’s chief executive Jack Fusco said in May the firm had still expected to commission the sixth unit at Sabine Pass by the end of 2021.

Moreover, the company expects substantial completion of the unit in the first half of 2022.

The 25 mtpa Sabine Pass plant has five operational trains and is currently the largest such facility in the US.

Bechtel is building the sixth train which will add 5 mtpa of capacity to the facility.

In total, this is the ninth train the engineering giant is building for Cheniere, including the Corpus Christi plant where Bechtel handed over the third train earlier this year.

- Advertisements -

Most Popular

QatarEnergy seals major deal with Chinese shipbuilder for 18 Q-Max LNG carriers

State-owned LNG giant QatarEnergy has signed a major shipbuilding deal with China State Shipbuilding Corp for the construction of...

TotalEnergies CEO: Mozambique LNG restart is not a matter of costs

French energy giant TotalEnergies had "good" discussions with Mozambique LNG contractors and they agreed not to inflate the costs...

Spot LNG shipping rates, European prices drop this week

Spot charter rates for the global liquefied natural gas (LNG) carrier fleet dropped slightly this week, while European and...

More News Like This

Woodside: largest compressor module arrives at Pluto Train 2 site

Australian LNG producer Woodside has received the largest compressor module from Indonesia at the Pluto Train 2 project site...

Flex clinches another LNG carrier charter extension

Norwegian shipping firm Flex LNG, the owner of 13 liquefied natural gas carriers, has secured a time charter extension...

Work progresses on NextDecade’s Rio Grande LNG export plant in Texas

US LNG firm NextDecade is moving forward with construction work on the first phase of its Rio Grande LNG...

Cheniere’s Corpus Christi LNG expansion project almost 53 percent complete

The Stage 3 expansion project at Cheniere's Corpus Christi LNG export plant in Texas is almost 53 percent complete,...