FERC suspends Kenai LNG environmental review

The US FERC is temporarily suspending an environmental assessment of a proposal to bring the closed Kenai LNG plant in Alaska back online as an import facility.

FERC said on April 8 it would suspend the environmental review for the project until the U.S. Pipeline and Hazardous Materials Safety Administration performs an “equivalency determination” related to a proposed vaporizer at the facility.

Marathon’s unit Trans-Foreland Pipeline proposes to the PHMSA to have the trim vaporizer within the LNG storage tank impoundment area.

FERC previously expected to issue an assessment for the Kenai import project on April 24. After that, the agency planned to make a decision by July 23.

The agency will now issue a revised schedule for the project once it can review the PHMSA documents, it said.

FERC said that this was not a suspension of its review of Trans-Foreland’s project.

“Staff will continue to process Trans-Foreland’s proposal to the extent possible based upon the information it has filed to date,” the agency said.

The fuel would go to an adjacent refinery

Trans Foreland filed an application with FERC back in March 2019.

It plans to make modifications to bring parts of Kenai LNG out of its current “warm idle status” to allow for imports.

The Kenai LNG cool down project would allow the plant to provide up to 7 million standard cubic feet per day of gas.

The fuel would be supplied to Trans-Foreland’s affiliated Kenai refinery adjacent to the LNG plant.

Trans-Foreland plans to add a new electric-driven boil-off-gas booster compressor unit, trim vaporizers and additional LNG transfer system valves.

ConocoPhillips sold the Kenai facility to a unit of Andeavor in February 2018.

Marathon completed its purchase of Andeavor in October 2018.

The Kenai plant was the only LNG export facility in North America for 47 years.

This was until Cheniere’s Sabine Pass export terminal in Louisiana entered service in February 2016.

The Kenai facility has not exported LNG cargoes since the fourth quarter of 2015.

Most Popular

QatarEnergy CEO says damaged Ras Laffan LNG trains to take three years to repair

State-owned LNG giant QatarEnergy expects the damage to two liquefaction trains at its giant Ras Laffan complex to take three years to repair, according to Qatar’s energy minister and CEO of QatarEnergy, Saad Sherida Al-Kaabi.

Hanwha Ocean, KR to develop LNG bunkering vessel concepts

South Korean shipbuilder Hanwha Ocean is teaming up with Korean Register (KR) to jointly develop two design concepts for an 18,000-cbm LNG bunkering vessel.

Maersk orders 26 LNG-powered container vessels

Danish shipping giant Maersk has ordered 26 LNG dual-fuel container vessels as it continues to expand its dual-fuel fleet.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project more than 50 percent complete

Cheniere's Corpus Christi Midscale Trains 8 and 9 project in Texas is more than 50 percent complete, according to the latest construction update.

Harvest expects to kick off Kenai LNG imports in 2029

Houston-based Harvest Midstream now expects to start liquefied natural gas (LNG) imports via the closed Kenai LNG export plant in Alaska in 2029, instead of 2028.

Construction progresses on Woodside’s Louisiana LNG project

Australian LNG player Woodside and its contractor Bechtel continue to advance construction of the first phase of the Louisiana LNG export terminal.

Glenfarne’s Magnolia LNG seals feed gas deal

Glenfarne’s Magnolia LNG has signed a long-term feed gas deal with Texas Eastern Transmission for its planned liquefaction and export plant in Louisiana.