LNG Croatia shuts Krk terminal for maintenance

State-owned terminal operator LNG Croatia said it has closed the Krk facility in the northern Adriatic Sea for its first maintenance turnaround since it started operations on January 1 this year.

“Starting from October 1, 2021 and for a period of 14 days, it will not be possible to use the jetty or regasification services due to the performance of regular annual maintenance work,” LNG Croatia said in a statement.

“According to the plan, the terminal should finish its maintenance work and start with regular operations on October 15, 2021 at 6:00 a.m.,” it said.

LNG Croatia did not provide any additional information.

The terminal includes the 140,000-cbm LNG Croatia FSRU, a jetty, and the connecting gas pipeline. It has the capacity to send up to 2.6 bcm per year of natural gas into the national grid.

To remind, the FSRU recently received an LNG cargo onboard the 174,000-cbm SCF Barents.

This shipment marked the 13th LNG cargo since the start of operations at the Krk facility on January 1 but also the eighth shipment from the US.

The LNG Croatia FSRU has also received two cargoes from Qatar and Nigeria, each, and one from Belgium’s Zeebrugge.

- Advertisements -

Most Popular

Sempra updates on Port Arthur LNG work

US LNG exporter Sempra and compatriot engineering and construction firm Bechtel are moving forward with construction on the first...

Chevron working to resume full Gorgon LNG production after ‘mechanical fault’

Chevron Australia, a unit of US energy giant Chevron, is working to resume full production from its Gorgon LNG...

Deutsche ReGas: FSRU leaves Lubmin to start Mukran job

The 2009-built 145,000-cbm, FSRU Neptune, has left Germany's industrial port of Lubmin and is expected to arrive in Mukran...

More News Like This

Croatian FSRU welcomes 90th LNG cargo

Croatia’s Krk liquefied natural gas (LNG) terminal has received its 90th cargo since the launch of operations in January...

Steel cut for Croatian regas module in China

Chinese shipbuilder Nantong CIMC Sinopacific Offshore & Engineering and a unit of Wartsila have officially started building one regasification...

Croatian FSRU welcomes 85th LNG cargo

Croatia’s Krk liquefied natural gas (LNG) terminal has received its 85th cargo since the launch of operations in January...

Croatian FSRU gets 80th LNG cargo

Croatia’s Krk LNG terminal has received its 80th liquefied natural gas cargo since the launch of operations in January...