Chevron to restart second Gorgon train in September

Chevron is looking to place back online the second train at its Gorgon LNG plant in Australia in September after it found “weld quality issues” within the propane heat exchangers.

The US energy firm shut down the second unit at its 15.6 mtpa LNG facility on Barrow Island in Western Australia on May 23 as part of planned maintenance.

It aimed to complete the maintenance works and restart the unit on July 11.

A Chevron spokesperson said in emailed comments on Tuesday that the company completed all the work but the train is still offline.

“A routine inspection of the Gorgon LNG Train 2 propane heat exchangers identified weld quality issues,” he said.

The train has in total eighth propane-fueled heat exchangers.

“Repairs are underway and we have the necessary personnel with skills and knowledge to conduct the work onsite,” the spokesperson said.

Chevron is working with the regulator, the Department of Mines, Industry Regulation and Safety, in planning and implementing this work.

“Once repairs are complete, we expect to safely commence LNG Train 2 restart activities around early September,” the spokesperson said.

In the meantime, Gorgon trains one and three are continuing to produce LNG.

The spokesperson added that Chevron continues to deliver LNG and domestic gas under its contractual commitments with customers.

Safety concerns

The news about the condition of the heat exchanges have been hitting the local media headlines for days.

The Australian Manufacturing Workers Union called on Chevron to shut down the plant due to safety concerns.

The union claims that “massive cracks with some up to a metre long” have been found on eighth exchangers.

Inspectors from the Western Australia regulator are expected to visit the Barrow Island LNG plant this week.

The Gorgon development is one of the world’s largest natural gas projects with a price tag of about $54 billion.

The LNG project sources gas from two offshore fields – Gorgon and Jansz-Io.

The first LNG cargo departed Barrow Island in March 2016 followed by gas supply to the domestic market in December.

Chevron’s Australian unit operates the project with a 47.3% share while ExxonMobil and Shell have a 25% stake, each.

Japan’s Osaka Gas, Tokyo Gas, and JERA own the remaining stakes in Gorgon.

Most Popular

BP, partners take FID on $7 billion Tangguh UCC project

BP said in a statement on Thursday the Tangguh Ubadari, CCUS, compression project (UCC) has the potential to unlock...

CoolCo seeks long-term employment for two LNG carriers

In August, Coolco said it plans to employ its first newbuild LNG vessel, Kool Tiger, on a shorter deal...

LNG Canada pipeline enters commercial service

Canada's TC Energy said on Tuesday CGL had executed a commercial agreement with LNG Canada and CGL customers that...

More News Like This

Kumul gets advance payment from Chevron for PNG LNG cargoes

Kumul said in a statement it recently closed an agreement with Chevron USA (Singapore Branch) that will further Kumul’s...

Chevron Australia says strike not expected to impact LNG production

The Offshore Alliance, which includes the Maritime Union of Australia and Australian Workers’ Union, said that its members working...

Wartsila, Chevron join forces to slash LNG carrier methane emissions

Wartsila said in a statement on Thursday the conversions are intended to reduce greenhouse gas emissions by lowering methane...

MOL, Chevron join forces on first wind-assisted LNG carrier

Japan's shipping firm MOL and a unit of US energy giant Chevron joined forces on what they say is...