Cheniere says 6th Sabine Pass LNG train almost complete

US LNG export firm Cheniere is nearing the completion of the sixth production train at its Sabine Pass liquefaction plant which will boost the Louisiana terminal’s capacity to 30 mtpa.

Cheniere said in its third quarterly report the project has achieved 97.1 percent completion as of September 30.

In September, Cheniere introduced feed gas to the unit after receiving approval from the Federal Energy Regulatory Commission (FERC).

The firm still expects to reach substantial completion at the 5 mtpa unit in the first quarter of next year.

Bechtel is building this train, such as the previous five units and the three trains at Cheniere’s Corpus Christi plant.

Adjusted Ebitda, revenues up

Cheniere said its adjusted Ebitda reached about $1.1 billion in the third quarter, compared to $477 million in the same period last year.

Revenues surged to $3.2 billion when compared to 1.46 billion last year, while the firm reported a net loss of about $1.1 billion, rising from $463 million in 2020.

The US LNG player said net income decreased $621 million primarily due to an increase in derivative losses from changes in fair value and settlements of $3.4 billion.

During the three and nine months ended September 30, Cheniere exported 500 TBtu and 1,476 TBtu of LNG, respectively, from its liquefaction projects.

Cheniere introduced full-year 2022 consolidated adjusted Ebitda guidance of $5.8 – $6.3 billion and distributable cash flow guidance of $3.1 – $3.6 billion.

“As we look ahead to 2022, we look forward to substantial completion on Train 6 at Sabine Pass in the first quarter, approximately a year ahead of the guaranteed completion schedule, fully realizing our original 9-train vision, and expanding on that platform with a positive FID on Corpus Christi Stage 3,” Cheniere’s chief executive Jack Fusco, said.

Most Popular

QatarEnergy CEO says damaged Ras Laffan LNG trains to take three years to repair

State-owned LNG giant QatarEnergy expects the damage to two liquefaction trains at its giant Ras Laffan complex to take three years to repair, according to Qatar’s energy minister and CEO of QatarEnergy, Saad Sherida Al-Kaabi.

Ecuador in LNG import move

Ecuador's state-run oil and gas company, Petroecuador, has invited international market participants to participate in a non-binding request for information to identify liquefied natural gas (LNG) supply alternatives that can help meet Ecuador’s growing natural gas demand.

FortisBC gets environmental approval for Tilbury LNG expansion

Canadian utility and operator of the Tilbury LNG facility in the province of British Columbia, FortisBC, has secured environmental approval for the Tilbury Phase 2 LNG expansion project.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project more than 50 percent complete

Cheniere's Corpus Christi Midscale Trains 8 and 9 project in Texas is more than 50 percent complete, according to the latest construction update.

Equinor takes first LNG cargo from Cheniere

Norwegian energy firm Equinor has taken delivery of its first liquefied natural gas (LNG) cargo under long-term supply agreements with US LNG exporting giant Cheniere.

Cheniere completes CCL Stage 3 project

US LNG exporter Cheniere has completed the Corpus Christi Liquefaction Stage 3 expansion project in Texas. In addition, Cheniere has also exported its 5,000th LNG cargo since 2016.

Germany’s BASF gets first LNG cargo under Cheniere contract

German chemicals giant BASF has received its first liquefied natural gas (LNG) cargo under a long-term contract with US LNG exporter Cheniere.