Chevron resumes production at first Gorgon LNG train

A unit of US energy giant Chevron said it has resumed production from the first train at its Gorgon LNG facility in Western Australia after it found a “minor” gas leak.

Chevron Australia temporarily suspended production from this 5.2 mtpa unit on November 16. The company said then it found the small leak on piping associated with the dehydration unit on the first train during routine operator duties at the LNG plant located on Barrow Island.

“Production at Gorgon LNG Train 1 has resumed following the completion of repair work on piping associated with the dehydration unit,” a Chevron spokesperson told LNG Prime in an emailed statement on Friday.

“Chevron worked systematically to safely address the issues and maintain natural gas to our customers and the Western Australian domestic market, the spokesperson said.

Investigation underway

The spokesperson said that “appropriate measures are in place to keep our workforce safe and a root cause investigation is underway.”

Chevron did not provide any additional information.

The firm has earlier this year completed repair works at the first train after it found “weld quality issues” within heat exchangers that closed the plant’s second and third production unit as well.

The firm said in late July it had completed repairing heat exchangers at the third Gorgon LNG train. Since then and prior to this leak, the plant had all three trains online.

Besides Gorgon, Chevron continues to produce LNG at both of its Wheatstone trains where it recently finalized the first major turnaround at the 8.9 mtpa plant near Onslow in Western Australia.

The Gorgon development is one of the world’s largest natural gas projects with a price tag of about $54 billion.

The giant 15.6 mtpa plant liquefies gas coming from two offshore fields – Gorgon and Jansz-Io.

The first LNG cargo departed Barrow Island in March 2016 followed by gas supply to the domestic market in December.

Chevron Australia operates the project with a 47.3% share while ExxonMobil and Shell have a 25% stake, each.

Japan’s Osaka Gas, Tokyo Gas, and JERA own the remaining stakes in Gorgon.

Most Popular

Duo competing to win New Zealand LNG terminal deal

New Zealand has shortlisted two providers to deliver its first liquefied natural gas (LNG) import terminal.

Hudong-Zhonghua kicks off construction on first QC-Max LNG carrier

Chinese shipbuilder Hudong-Zhonghua has officially started building the first ultra-large QC-Max LNG carrier as part of the massive QatarEnergy shipbuilding program. The shipbuilder says this is the world's largest LNG carrier.

South Korea’s Samsung Heavy clinches another LNG carrier order

South Korean shipbuilding giant Samsung Heavy Industries has secured an order to build another liquefied natural gas (LNG) carrier for approximately $252 million.

More News Like This

MOL’s newbuild LNG carrier gets sails in South Korea

South Korea's Hanwha Ocean has completed the world’s first installation of the wind challenger system on an LNG carrier. The LNG carrier is owned by Japan's MOL and chartered by US energy giant Chevron.

Chevron resumes full Wheatstone LNG production after repairs

Chevron has resumed full production at the Wheatstone LNG facility near Onslow in Western Australia following the completion of repairs after Tropical Cyclone Narelle.

Chevron says Wheatstone LNG plant operating at 50 percent capacity

Chevron's Wheatstone LNG facility near Onslow in Western Australia is now operating at 50 percent capacity, while repairs continue on the second liquefaction train, a Chevron Australia spokesperson told LNG Prime on Thursday.

Chevron says all Gorgon LNG trains operating, Wheatstone damaged

All three liquefaction trains at Chevron's giant Gorgon LNG plant on Barrow Island are now operational following a powerful tropical cyclone in Western Australia, a Chevron Australia spokesperson told LNG Prime on Sunday.