Pembina axes Jordan Cove LNG export project

Canadian energy firm Pembina Pipeline said it would not move forward with its proposed Jordan Cove LNG export plant and related pipeline in Oregon.

The Jordan Cove LNG export terminal on the US West Coast has received final approval from federal authorities last year, but it was not able to obtain the necessary state permits.

Pembina said in April this year it had paused the project as it could not secure permits and authorizations from various Oregon state agencies.

The company’s units Jordan Cove Energy Project and Pacific Connector Gas Pipeline revealed this new decision in a filing with FERC dated December 1.

The applicants filed at FERC addressing whether the commission should stay the authorizations.

“Applicants are requesting that the commission vacate the authorizations issued in this proceeding, which would then moot the question of whether to stay the certificate authorization granted to PCGP,” they said.

On January 19, the commission issued an order denying applicants’ petition for declaratory
order, determining that Oregon had not waived its Clean Water Act Section 401 certification
authority.

Subsequently, on February 8, the Department of Commerce sustained Oregon’s objection under the Coastal Zone Management Act.

Since those orders, the developers said they have undertaken a review of permitting developments and the prospects for obtaining the permits in the future.

“Applicants have now completed this review and have decided not to move forward with
the project,” they said.

Canada’s Pembina had planned to export up to 1.08 billion cubic feet per day from the LNG terminal in Oregon.

The project would have included a 229-mile pipeline traversing four counties in Southern Oregon, and the 7.8 mtpa LNG export terminal in Coos Bay.

Most Popular

YPF CEO: FID on second Argentina FLNG expected by July

Pan American Energy, Golar LNG, YPF, Pampa Energia, and Harbour Energy plan to take a final investment decision on Argentina's second floating LNG production unit by the end of July, according to YPF CEO Horacio Marin.

Sempra still targets Port Arthur LNG expansion FID in 2025

Sempra Infrastructure, a unit of Sempra, still expects to make a final investment decision on the second phase of its Port Arthur LNG export project in Texas in 2025.

Germany, Egypt seal FSRU charter deal

Germany's Ministry for Economic Affairs and Energy has signed a deal with Egypt's state-owned EGAS to charter the 174,000-cbm FSRU Energos Power.

More News Like This

Pembina CEO sees enough demand for Cedar LNG expansion

Canada’s Pembina Pipeline sees enough demand for a potential second phase of the Cedar LNG project, according to Scott Burrows, president and CEO of Pembina.

US FERC issues final SEIS for Venture Global’s CP2 LNG project

The US Federal Energy Regulatory Commission (FERC) has released a final supplemental environmental impact statement for Venture Global LNG's proposed CP2 LNG project in Louisiana. The regulator concluded that there would be no significant cumulative air quality impacts from the project.

Energy Transfer’s Lake Charles LNG secures FERC extension

Texas-based Energy Transfer has secured an extension of time from the US FERC to complete and place into service its planned Lake Charles LNG export facility in Louisiana.

Venture Global’s Plaquemines LNG to commission third tank

US LNG exporter Venture Global LNG is seeking approval from the US FERC to commission the third storage tank with LNG at its Plaquemines plant in Louisiana.