Cheniere seeks more time for Corpus Christi LNG expansion

US LNG exporting giant Cheniere asked US energy regulators for an extension to construct the proposed Stage 3 expansion at its Corpus Christi export plant in Texas.

The Corpus Christi liquefaction plant now consists of three operational trains with each having a capacity of about 5 mtpa.

Under the expansion project, Cheniere plans to build up to seven mid-scale liquefaction trains with a total expected nominal production capacity of about 10 mtpa.

The US FERC approved this expansion project back in November 2019. Under this approval, Cheniere and its units have to complete the project in five years or until around November 2024.

Cheniere’s units asked FERC in a filing dated December 7 to extend this date until June 2027.

“The onset and duration of the Covid-19 pandemic resulted in adverse economic and logistical conditions that slowed commercial progress and precluded CCL Stage III from making a timely final investment decision (FID) on the Stage 3 project in order to meet the current permitted construction duration,” Cheniere said in the filing.

This delay in full commercialization has resulted in the need for additional time to construct and place the Stage 3 project in service, Cheniere said.

Close to FID

While the Covid-19 pandemic caused significant impact to global markets last year, global LNG demand and long-term contracting activity have experienced significant growth in 2021, according to Cheniere.

“During the last 12 months alone, Cheniere Energy and its affiliates have signed about 6 mtpa of long-term contracts, which, alongside long-term contracts previously signed, means that commercialization for the Stage 3 project is close to completion,” it said.

The strong global LNG market continues to drive commercial momentum, and CCL Stage III
anticipates “imminently restarting” early construction activities at the Stage 3 project site and making a positive FID during 2022, Cheniere said.

Full construction of the expansion facilities would commence upon making a positive FID.

Based on a June 2022 FID and a 60-month construction duration, the Stage 3 project would be made available for service by June 2027, Cheniere said.

Most Popular

Daniel Kalms leaves Woodside

Woodside's executive vice president and chief operating officer international, Daniel Kalms, is leaving the Australian LNG player.

Lithuania’s Ignitis to sign long-term LNG supply deal with EQT

Lithuanian state-controlled energy company Ignitis will sign a long-term LNG supply and purchase agreement with a unit of US natural gas producer EQT following the completion of a tender.

Exmar’s FSU heads to Colombia

Exmar's newly converted 146,000-cbm floating storage unit, Tura, is en route to Colombia to begin operations as part of Regasificadora Del Pacífico's LNG import project on Colombia's west coast.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project more than 50 percent complete

Cheniere's Corpus Christi Midscale Trains 8 and 9 project in Texas is more than 50 percent complete, according to the latest construction update.

Equinor takes first LNG cargo from Cheniere

Norwegian energy firm Equinor has taken delivery of its first liquefied natural gas (LNG) cargo under long-term supply agreements with US LNG exporting giant Cheniere.

Cheniere completes CCL Stage 3 project

US LNG exporter Cheniere has completed the Corpus Christi Liquefaction Stage 3 expansion project in Texas. In addition, Cheniere has also exported its 5,000th LNG cargo since 2016.

Germany’s BASF gets first LNG cargo under Cheniere contract

German chemicals giant BASF has received its first liquefied natural gas (LNG) cargo under a long-term contract with US LNG exporter Cheniere.