Nigeria’s UTM Offshore plans to take FLNG FID in Q4 2022, CEO says

UTM Offshore is looking to take a final investment decision on Nigeria’s first floating LNG project in the fourth quarter of 2022, according to the company’s managing director and chief executive, Julius Rone.

Abuja-based UTM Offshore has just signed a deal with the African Export-Import Bank (Afreximbank) to secure up to $5 billion for the development of the FLNG project.

The company is targeting to launch the project in 2026.

“UTM is expected to take the final investment decision (FID) and award engineering, procurement, construction and installation (EPCI) contract in the fourth quarter of 2022,” Rone told LNG Prime on Thursday.

Capacity boost

Rone said that Japan’s JGC has completed the pre-front end engineering and design work for the FLNG awarded earlier this year.

The firm also selected US-based KBR as the owner’s engineer to review JGC’s work and said that trader Vitol had joined the consortium as off-taker for the LNG.

JGC completed the pre-FEED work on October 15, some four months after it started the project.

As a result of this design work, the FLNG’s capacity would be boosted by some 26 percent to 1.52 mtpa, according to Rone.

UTM Offshore previously said it would install a liquefaction unit with a capacity of 1.2 mtpa, sourcing gas from the Yoho field which lies in Oil Mining Lease 104, offshore Nigeria.

Also, the unit would process associated gas currently flared in order to cut carbon emissions and monetize additional reserves for the domestic and global market.

The facility would receive gas from an existing offshore platform located at OML 104.

The Nigerian government holds a 60 percent interest in the Yoho crude oil joint venture, through NNPC, while ExxonMobil’s MPN holds the remaining 40 percent and operates the development that started production back in 2003.

FLNG newbuild

Rone said that a newbuild unit would serve the first FLNG project developed by an African company on the continent.

He said the unit would have a turret and mooring system, gas pretreatment and LNG production modules, living quarters, self-contained power generation and utilities, as well as capacities for LNG storage and offloading.

JGC’s preferred partner for FLNG projects is South Korea’s Samsung Heavy Industries.

The two firms have already delivered the second FLNG for Petronas and they are working together on the FEED for the third Petronas’ FLNG as well. SHI and JGC also partnered with Technip Energies on the recently delivered Coral FLNG, owned by Eni.

Rone did not comment when asked whether SHI could build the unit with JGC.

UTM Offshore’s FLNG would add to the 22 mtpa of LNG capacity the Bonny onshore plant already produces in Nigeria.

Besides the six existing trains, the joint venture behind the Bonny plant which includes NNPC, Shell, Total, and Eni is also building an additional unit to boost the terminal’s capacity to 30 mtpa.

Most Popular

Another steam LNG carrier sold for demolition

An NYK-managed steam liquefied natural gas (LNG) carrier has been sold for demolition, according to brokers.

Canada approves Ksi Lisims LNG project

According to a statement on Monday, Julie Dabrusin, Minister of Environment and Climate Change, issued her decision under the...

GasLog, Woodside name LNG carrier duo in South Korea

South Korea's Hanwha Ocean has hosted a naming ceremony at its yard in Geoje for two LNG carriers it built for owner Greece's GasLog and charterer Australia's Woodside.

More News Like This

JGC inks LNG cooperation deal with Tanzania

Japan’s LNG engineer JGC has signed a memorandum of understanding with the government of Tanzania on sharing LNG plant expertise and other cooperation.

Inpex awards FEED contracts for Abadi onshore LNG plant

Japan's Inpex has awarded contracts to two contractor consortia for the front-end engineering design (FEED) work for the onshore LNG plant as part of the Abadi LNG project in Indonesia. The contractors include JGC and Technip Energies, and KBR, Samsung E&A, and Adhi Karya (Persero).

Inpex launches Abadi LNG FEED work

Japan's Inpex has launched the front-end engineering design (FEED) work for the Abadi LNG project in Indonesia. The contractors include Technip Energies, JGC, Saipem, Tripatra, McDermott, and Worley.

Fluor, JGC score FEED job for LNG Canada expansion

A joint venture of US engineer Fluor and Japan's JGC has been awarded the contract to update the front-end engineering and design (FEED) for a proposed Phase 2 expansion of the Shell-led LNG Canada project.