Energy Transfer seeks more time to build Lake Charles LNG export plant

Energy Transfer asked US energy regulators for a three-year extension to construct its proposed Lake Charles LNG export facility in Louisiana.

The Lake Charles LNG project seeks to convert Energy Transfer’s existing regasification terminal to an LNG export facility.

It has a proposed liquefaction capacity of 16.45 million tonnes per year and includes three trains and modifications to the Trunkline Gas pipeline.

LNG giant Shell announced a decision to pull out of the project back in 2020.

Following the Shell decision, Energy Transfer said it would evaluate various alternatives to advance the LNG project including bringing new partners and reducing the plant’s size.

Energy Transfer seeks more time to build Lake Charles LNG export plant
Image: Energy Transfer

In 2019, the company has sought and won an approval from the US FERC for a five-year extension to build the LNG terminal until December 2025.

Now, its units developing the LNG export facility and the pipeline are seeking to extend that deadline until 2028, according to a filling with the FERC dated February 3.

“The applicants state that global market conditions have impacted its ability to reach a final investment decision and secure long-term offtake contracts, thus they now request an additional three years, until December 16, 2028, to complete construction of the project and place it into service,” they said.

Most Popular

Novatek installs Arctic LNG 2 GBS

Russian LNG exporter Novatek has completed the installation of the first gravity-based structure platform which will serve its Arctic...

Cheniere inks long-term LNG supply deals with QatarEnergy

US LNG exporter Cheniere has entered into long-term liquefied natural gas (LNG) sale and purchase agreements with state-owned LNG giant QatarEnergy to supply 4 million tonnes per annum (mtpa) of LNG through 2054.

NFE in Puerto Rico LNG supply contract dispute

The Puerto Rico Electric Power Authority (PREPA) and US LNG player New Fortress Energy are in dispute over liquefied natural gas (LNG) deliveries under their long-term LNG supply deal, according to the Financial Oversight and Management Board for Puerto Rico.

More News Like This

US FERC launches first LNG authorization program

The US Federal Energy Regulatory Commission (FERC) proposed accelerating liquefied natural gas (LNG) infrastructure development through a blanket authorization program.

Venture Global gets approval to place first Plaquemines LNG phase in service

Venture Global’s Plaquemines LNG has secured approval from the US FERC to place Phase 1 of its LNG export plant in Louisiana into service.

Cheniere’s Corpus Christi Trains 8 and 9 project 55.6 percent complete

US LNG exporter Cheniere continues to progress construction on its Corpus Christi Midscale Trains 8 and 9 project in Texas.

Venture Global seeks FERC OK to place first Plaquemines LNG phase in service

Venture Global's Plaquemines LNG is seeking approval from the US FERC to place Phase 1 of its LNG export plant in Louisiana into service.