Zvezda starts building seventh Arctic LNG 2 carrier

Russian Zvezda yard has started working on another ice-class Arc7 carrier that will serve the Novatek-operated Arctic LNG 2 project.

The yard held a steel-cutting ceremony on February 4 for the seventh carrier out of fifteen on order, it said in a statement.

Also, Zvezda will deliver this 172,600-cbm vessel in September 2024.

To remind, Zvezda started to work on the first vessel in November 2020. Russia’s largest shipping firm Sovcomflot ordered this vessel directly at the compatriot yard.

Novatek, Sovcomflot and VEB.RF finalized the construction and charter deals for the other 14 vessels with Zvezda in September 2020.

Additionally, Arctic LNG 2 entered into a charter deal for the vessels with SMART LNG, a venture consisting of Novatek and Sovcomflot.

Zvezda starts building seventh Arctic LNG 2 carrier
Image: Zvezda

Zvezda is building all of these vessels in a partnership with South Korea’s Samsung Heavy Industries that provides technological support.

The LNG carriers will operate under the Russian flag and they will be 300 meters long but also 48.8 meters wide, and feature GTT’s Mark III membrane containment system.

In addition, the propulsion system includes three azimuth units with a total capacity of 45 MW.

The construction of these LNG carriers will ensure year-round transport of LNG along the Northern Sea Route to the Asia-Pacific region.

The Arctic 2 LNG project located on the Gydan peninsula includes the construction of three LNG trains with a capacity of 6.6 mtpa, each, using gravity-based structure platforms.

Novatek expects to launch the first LNG train in 2023, with trains 2 and 3 to follow in 2024 and 2025, respectively.

- Advertisements -

Most Popular

Chevron working to resume full Gorgon LNG production after ‘mechanical fault’

Chevron Australia, a unit of US energy giant Chevron, is working to resume full production from its Gorgon LNG...

Commissioning of India’s Chhara LNG terminal delayed

India’s Hindustan Petroleum, a unit of state-owned ONGC, has reportedly delayed the commissioning of its Chhara LNG import terminal...

Tellurian’s net loss widens in Q1, Driftwood LNG talks continue

US LNG firm Tellurian reported a widening first-quarter loss on Thursday, as it continues to work to secure financing...

More News Like This

TotalEnergies CEO: Mozambique LNG restart is not a matter of costs

French energy giant TotalEnergies had "good" discussions with Mozambique LNG contractors and they agreed not to inflate the costs...

Russia’s Gazprom to buy Shell’s stake in Sakhalin LNG terminal operator

Russia has approved the sale of a 27.5 percent stake, previously owned by LNG giant Shell, in the new...

Novatek reports profit of about $5.1 billion in 2023

Russian LNG producer Novatek reported a net profit of about 463 billion rubles ($5.09 billion) in 2023. The company...

TotalEnergies issues force majeure over Novatek’s Arctic LNG 2 project

French energy giant TotalEnergies has initiated a force majeure process on the Novatek-operated Arctic LNG 2 project in Russia...