Bechtel hands over sixth Sabine Pass train to Cheniere

Bechtel has handed over operational control of the sixth train at the Sabine Pass export plant in Louisiana to Cheniere, marking the substantial completion of the liquefaction unit.

Cheniere Partners, a unit of Cheniere, took over care, custody, and control of Train 6 on February 4, according to a statement on Monday.

This follows the start of production at the 5 mtpa new unit in late November and the first LNG cargo in December.

Bechtel built the previous five units and the three trains at Cheniere’s Corpus Christi plant.

Sabine Pass now has total production capacity of about 30 mtpa of LNG.

“The accelerated completion of Train 6 once again reflects the world-class standard of execution consistently achieved by the Cheniere and Bechtel teams, and we are proud to have the six train vision of Sabine Pass completed safely, ahead of schedule and on budget,” said Jack Fusco, CEO of Cheniere.

“With nine total trains across both the Sabine Pass and Corpus Christi projects, the Cheniere liquefaction platform is the second largest in the world,” Fusco said.

Most Popular

Adnoc launches LNG marketing and trading platform

UAE's energy giant Adnoc has launched a global liquefied natural gas (LNG) marketing and trading platform, targeting 47 million tonnes per annum (mtpa) of combined marketable LNG by 2035.

Glenfarne’s commodities unit, BGN ink preliminary LNG supply deal

Glenfarne's unit Glenfarne Global Commodities has signed a heads of agreement with Switzerland-based energy trader BGN for the long-term supply of liquefied natural gas (LNG).

Kiewit gets limited notice to proceed for Glenfarne’s Texas LNG

US construction and engineering firm Kiewit has received a limited notice to proceed from Glenfarne's Texas LNG for the latter's planned 4 mtpa LNG export terminal in the port of Brownsville.

More News Like This

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.

Cheniere’s Corpus Christi Stage 3 project 98 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 98 percent complete, as it continues to progress ahead of schedule, according to the latest construction update.

Cheniere progresses commissioning of seventh Corpus Christi expansion train

US LNG exporting giant Cheniere is moving forward with commissioning activities at the seventh train of the Corpus Christi Stage 3 expansion project in Texas.

Cheniere completes sixth train at Corpus Christi expansion project

US LNG exporter Cheniere has reached substantial completion of the sixth liquefaction train at the Corpus Christi Stage 3 expansion project in Texas.