Chinese yard delivers first Croatian FSRU

China’s Huarun Dadong yard has completed the conversion works on Croatia’s first FSRU which will soon depart to its base on the island of Krk in the northern Adriatic Sea.

The vessel named LNG Croatia brings the European country one step closer to joining the growing club of worldwide LNG importing nations with the official launch of the Krk facility expected on January 1, 2021.

Huarun Dadong and its shareholder CSSC Hudong-Zhonghua delivered the FSRU to Golar and the state-owned Krk terminal developer LNG Croatia on Tuesday.

Golar won a deal last year to provide its 2005-built 140,205-cbm vessel Golar Viking to the Krk project and convert it to a FSRU.

After that, the LNG firm tapped Hudong-Zhonghua to perform conversion works and agreed a $160 million sale and leasback deal for the vessel with CSSC Leasing, the leasing unit of China State Shipbuilding Corporation.

The ship arrived at the Huarun Dadong yard near Shanghai in January this year and reached completion some nine months later.

Chinese yard delivers first Croatian FSRU
The delivery ceremony (Image: Huarun Dadong Dockyard)

Golar’s chief executive Iain Ross said last month the firm expected the vessel to depart from China to Krk late September.

Following arrival and commissioning at the Krk facility later this year, Golar will officially hand over the FSRU to LNG Croatia but will continue operating and maintaining the unit for ten years.

Most of capacities booked, Shell one of the suppliers

Croatia’s first LNG terminal will have a capacity to send up to 2.6 bcm per year of natural gas into the national grid.

LNG Croatia previously said it would complete onshore works which include a jetty and a high-pressure gas pipeline by November, just in time when the FSRU arrives.

Chinese yard delivers first Croatian FSRU
Krk LNG jetty (Image: LNG Croatia)

Furthermore, the terminal developer also revealed that all of the terminal’s capacities have been booked for the next three years.

The capacity takers include Hungary’s state-owned MFGK and trading firm MET.

Worth mentioning here, Hungary said earlier this month the country signed a deal with LNG giant Shell to receive natural gas via the Krk facility as part of the MFGK booking.

Additionally, Qatar’s PowerGlobe, the energy arm of privately-held Optimized Holding, booked the largest capacity at Krk spanning a period of 15 years.

The LNG import project costs 233.6 million euros ($276.8 million) with EU providing 101.4 million euros from the Connecting Europe Facility.

Most Popular

Shell wraps up acquisition of Pavilion Energy

UK-based LNG giant Shell has completed its previously announced acquisition of Singapore's Pavilion Energy.

India’s ONGC approves Mozambique LNG investment

India’s state-run ONGC has approved an investment by its unit, ONGC Videsh, into the TotalEnergies-led Mozambique LNG joint venture, which is developing a 12.8 mtpa liquefaction plant at the Afungi complex.

Australia’s Viva Energy seeks FSRU for Geelong project

Australia’s Viva Energy is looking to secure a floating storage and regasification Unit (FSRU) for its proposed LNG import terminal in Geelong, Australia.

More News Like This

CIMC SOE completes Croatian regas module

Chinese shipbuilder Nantong CIMC Sinopacific Offshore & Engineering has completed Wartsila's regasification module that will be installed onboard the 140,000-cbm FSRU, LNG Croatia.

QatarEnergy LNG carrier completes trials in China

A 174,000-cbm liquefied natural gas (LNG) carrier built as part of the massive QatarEnergy shipbuilding program has completed its trials in China, according to Hudong-Zhonghua.

Croatia completes new LNG pipeline

Croatia has completed the Zlobin-Bosiljevo gas pipeline as part of the capacity expansion project of the FSRU-based LNG import facility on the island of Krk.

Croatian FSRU in new LNG truck loading milestone

State-owned LNG Croatia, the operator of the FSRU-based Krk import facility, has completed the 500th LNG reloading operation directly from the vessel to a truck.