NextDecade seeks more time to build Rio Grande LNG export plant

NextDecade asked US energy regulators for a two-year extension to construct its proposed Rio Grande LNG export plant in Texas.

In 2019, the company won approval from the US FERC to build the LNG terminal with up to five trains and a total capacity of 27 mtpa by November 22, 2026.

Now, NextDecade is seeking to extend that deadline until November 22, 2028, according to a FERC filing dated April 6.

NextDecade told FERC that Rio Grande LNG was impacted by “unforeseeable developments in the global LNG market as a result of the Covid-19 pandemic, including major disruptions in world energy markets due to a temporary but significant demand destruction resulting from global lock-downs.”

According to the company, the pandemic has affected the ability of Rio Grande LNG to enter into additional long-term offtake contracts with customers sufficient to enable the company to achieve a final investment decision (FID).

More LNG supply contracts to come

However, despite the pandemic, commercialization of Rio Grande LNG has accelerated in the past quarter, NextDecade said.

The company revealed two LNG supply deals with Chinese firms in the last two weeks.

Under the first 20-year HoA announced on March 24, NextDecade would supply up to 1.5 mtpa of LNG indexed to Henry Hub to Guangdong Energy Group Natural Gas.

After that, the Rio Grande developer said it had signed a deal to supply liquefied natural gas to a unit of Chinese independent gas distributor ENN.

Under this 20-year sales and purchase deal, ENN LNG would buy 1.5 mtpa of LNG indexed to Henry Hub on a free-on-board basis.

The LNG supply would come from the first two Rio Grande trains with a capacity of 11 mtpa.

Besides these deals, NextDecade said it expects to execute more contracts over the next quarter.

Following a recent deal, the US will work to supply at least 15 billion cubic meters (bcm) of LNG to European Union markets this year, as the EU looks to slash dependence on Russian gas.

NextDecade said Rio Grande LNG would “play an important role in meeting Europe’s
demand for LNG.”

The company added it anticipates beginning construction and making a positive FID on a minimum of two trains in the second half of 2022.

Most Popular

US DOE releases LNG export study

The Biden administration said in January it will pause pending decisions on exports of LNG to non-FTA countries until DOE can...

GTT CEO: LNG carrier replacement market poised for significant growth

Choimet officially took over as GTT CEO in June this year and has since then been on the road...

Seatrium, Golar agree to let third FLNG conversion contract lapse

Seatrium, previously known as Sembcorp Marine and renamed as Seatrium following its merger with Keppel Offshore & Marine, revealed this in a...

More News Like This

Construction advances on Sempra’s Port Arthur LNG export terminal

In March last year, Sempra Infrastructure, a unit of Sempra, took a final investment decision for the first phase of its...

US FERC to prepare supplemental EIS for Venture Global’s CP2 LNG project

In July last year, the regulator issued a final environmental impact statement for the CP2 LNG project, Venture Global’s third LNG...

Cheniere’s Corpus Christi LNG expansion project to receive first gas

The US FERC said on Wednesday that it had granted Corpus Christi Liquefaction's request to introduce hydrocarbons to Train...

Construction progresses on NextDecade’s Rio Grande LNG project

Schatzman said in a third-quarter business update that the facility "continues to progress safely, in line with schedule, and...