Finland’s Hamina LNG terminal nearing completion

Hamina LNG said it plans to launch commercial operations at its delayed LNG import terminal in the Hamina port in October this year.

The LNG terminal developer is a joint venture consisting of Finland’s Hamina Energy, tech firm Wartsila, and Estonia’s energy company Alexela.

In order to carry out the finishing work for the Hamina LNG terminal, the firm said in a statement released on Monday it has concluded a contract with Finland’s Viafin Process Piping.

Following completion of the work, the terminal would launch a commissioning phase aiming at commercial use in October 2022, Hamina LNG said.

Viafin has been involved in the LNG terminal project from the beginning. The firm was responsible for the mechanical installations outside the terminal’s 30,000-cbm tank, Hamina LNG said.

Construction work on the facility started in October 2017, while the partners held a groundbreaking ceremony in September 2018.

The partners previously delayed the launch of the terminal in 2020 and 2021.

According to a statement posted by Hamina LNG in February this year, the JV had decided to dissolve the contract with Wartsila, which had previously served as the main contractor of the facility.

Instead, the JV said Germany-based TGE Gas Engineering, which worked as a technical consultant for Hamina LNG, would continue to support the project, the statement said.

Plans to boost capacity

Hamina LNG says this facility is currently the only LNG import terminal in Finland connected to the country’s natural gas transmission system.

Besides this facility, Finland has the Pori and Tornio LNG terminals.

The facility in Hamina will be able to receive LNG vessels with a capacity of 5,000 cbm to 25,000 cbm and has a truck loading station.

Following completion, the facility would supply about 3 TWh per year to the grid, but there are plans to increase the capacity, according to Hamina LNG.

In addition to grid supply, distribution of gas by road transport could reach a volume of 3 TWh per year, boosting the facility’s throughput in the initial stage to as much as 6 TWh per year, Hamina LNG said.

Also, Hamina LNG said it has started planning work to gradually increase the supply capacity of the facility.

Hamina LNG says it could double the supply capacity to the transmission network this year, and in the next stage to further increase it to a level of about 7 TWh per year.

After this, the terminal has the capabilities to increase the supply capacity to the grid even more, it said.

The launch of the facility comes at a time when Finland is looking to reduce its reliance on Russian gas supplies.

In that regard, Finland and Estonia are also planning to jointly charter a floating storage and regasification unit (FSRU) to import LNG.

Most Popular

Cheniere’s Corpus Christi Trains 8 and 9 project more than 50 percent complete

Cheniere's Corpus Christi Midscale Trains 8 and 9 project in Texas is more than 50 percent complete, according to the latest construction update.

Daniel Kalms leaves Woodside

Woodside's executive vice president and chief operating officer international, Daniel Kalms, is leaving the Australian LNG player.

DNV says LNG bunkering fleet may need to more than double by 2030

The global LNG bunkering vessel fleet may need to more than double by 2030 as demand from LNG-fueled ships grows faster than the infrastructure required to supply them, according to classification society DNV.

More News Like This

Gasum’s Borlange bio-LNG plant enters commissioning phase

Gasum’s new bio-LNG production plant in Borlange, Sweden, has entered the commissioning phase, according to Lundsby Renewable Solutions.

Wartsila to support Carnival’s LNG-powered vessels

Finland’s tech firm Wartsila has signed a deal with US-based cruise operator Carnival to support the latter’s four LNG-powered cruise vessels.

Roof raised on Shenzhen LNG tank in China

China’s city gas distributor Shenzhen Gas and its contractors have completed raising the roof on one of two LNG storage tanks as part of the Shenzhen LNG storage and peak shaving II expansion project.

Mutares completes acquisition of Wartsila’s gas solutions unit

German private equity investor Mutares has completed the previously announced aqisition of Wartsila's gas solutions business