Shell’s LNG Canada almost 28 percent complete

The Shell-led LNG Canada development is moving forward despite disruptions caused by the Covid-19 pandemic. The total project progress reached about 27.5 percent, according to the main contractor Fluor.

To remind, Fluor and partner JGC hold the engineering, procurement and construction contract on the LNG export project worth more than $30 billion.

Following the FID by Shell and partners back in October 2018, the duo started working at the project site in Kitimat.

The two firms continued to perform works until March this year when they were forced to downsize the workforce by half due to the pandemic.

“In keeping with the local regulations, we had a considerable workforce reduction in mid-March, but work with the provincial governments, multi-phase reached our plant to resume activities,” Fluor chief executive Carlos Hernandez said during a recent investor call

“We’re pleased to report that our workforce is now back where it was before the drawdown, and we expect to increase it to 2,500 on-site by the end of 2020,” he said.

However, these events have caused delays within the giant LNG project.

“LNG Canada is, it is behind because of the pandemic,” Hernandez said, adding that the JV was in talks with Shell regarding the timeline.

Hernandez did not provide any additional information regarding the delays. But, according to LNG Canada, they will not affect the first LNG shipment expected in the middle of the decade.

“Works progressing well”

Despite Covid-19, works on the Kitimat site have been progressing “very well,” Hernandez said.

According to the CEO, the project is about 27.5% complete. This is on an overall basis and observed from the engineering, procurement, construction, and fabrication point of view.

“Now, obviously, that’s not construction, construction is less than that. But, we’re comfortable with the progress that has been made to date,” he said.

Shell's LNG Canada almost 28 percent complete (2)
Image: Fluor

Looking at recent milestones, the JGC Fluor team reached first concrete pour for the base of the LNG storage tank.

Once complete, the 225,000-cbm tank will be approximately 60 meters tall and 100 meters in diameter.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation and Kogas of South Korea.

LNG Canada will initially include two trains with the capacity to produce 14 million tonnes of LNG per year.

Most Popular

Technip Energies wins contract for Eni’s Coral Norte FLNG

France-based LNG engineering giant Technip Energies has won a contract for preliminary work on Eni's second FLNG project in Mozambique, Coral Norte (Coral North).

Victrol: LNG London hits bunkering milestone

The Shell-chartered inland bunkering vessel LNG London, owned by a joint venture of Belgium's Victrol and France's Sogestran, has reached a new operational milestone.

Himalaya’s LNG-fueled bulkers earned $34,500 per day in June

LNG-powered bulker owner Himalaya Shipping achieved average time charter equivalent earnings of about $34,500 per day in June.

More News Like This

Victrol: LNG London hits bunkering milestone

The Shell-chartered inland bunkering vessel LNG London, owned by a joint venture of Belgium's Victrol and France's Sogestran, has reached a new operational milestone.

Monadelphous scores new LNG contracts

Australian engineering firm Monadelphous has secured contracts for Shell's Crux natural gas project offshore Western Australia and the Australia Pacific LNG project in Queensland.

European network of LNG stations reaches new milestone

Europe's network of liquefied natural gas (LNG) fueling stations for vehicles has surpassed 800 stations, according to Eurogas.

Former Shell CFO joins BP’s board

UK-based energy giant BP has appointed Simon Henry, Shell's former finance chief, to its board as a non-executive director.