Tellurian awards pipeline gig to Baker Hughes

US LNG firm Tellurian, developer of the Driftwood LNG export facility in Louisiana, said that its unit Driftwood Pipeline has awarded a contract to compatriot energy services firm Baker Hughes.

Under the deal, Baker Hughes will provide electric-powered integrated compressor line (ICL) technology and turbomachinery equipment for Lines 200 and 300, a natural gas transmission project, proposed to be located in Beauregard and Calcasieu Parishes, in southwest Louisiana.

According to a statement by Tellurian, this contract marks the first time Baker Hughes would install its ICL decarbonization technology for pipeline compression in North America.

The project will initially include four 19 megawatt (MW) ICL compressors and other turbomachinery equipment for a total of four compressor trains.

Also, the scope includes a LM6000PF+ gas turbine for backup power for the initial phase of the pipeline project at Driftwood’s Indian Bayou Compressor Station.

$240 million pipeline investment

“This landmark project and technology will eliminate nearly all emissions for the proposed project, which Tellurian is developing to supply natural gas to a constrained capacity area,” Tellurian CEO Octavio Simoes said in the statement.

Joey Mahmoud, president of Tellurian Pipelines, said the firm expects the project would supply upwards of five and one-half billion cubic feet of natural gas daily, with “virtually no emissions”.

“Tellurian is doing its part by making this initial $240 million pipeline investment as part of the broader Driftwood Pipeline system which will provide enhanced supply reliability to meet the area’s projected industrial growth in a cleaner, more sustainable manner,” Mahmoud said.

In March, Tellurian issued a limited notice to proceed to Bechtel under its executed EPC contract to begin construction of phase one of the Driftwood LNG plant.

Phase one of the project will include two LNG plants near Lake Charles with an export capacity of up to 11 million tonnes per annum (mtpa), while the full project would have 27.6 mtpa liquefaction capacity.

Tellurian already signed three 10-year LNG supply deals for the Driftwood project for a total of 9 mtpa. These include contracts with Gunvor, Vitol as well as Shell.

The firm is still working on the financing of the project in which it already invested about $750 million.

Most Popular

Delfin takes FID on first FLNG

Delfin Midstream has taken a final investment decision for the first 4.4 mtpa floating liquefied natural gas unit of its LNG project under development in Louisiana. Delfin says the FLNG is the first floating liquefaction facility in the United States and the world's largest FLNG.

Malaysia’s Petronas Gas, Integrax ink pact for new LNG import terminal

Malaysia's Petronas Gas, a unit of Petronas, has signed a binding deal with compatriot Integrax, a part of TNB Power Generation, to jointly develop the country's first FSRU-based LNG import terminal in Lumut, Perak.

Samsung Heavy secures FLNG order from Delfin

South Korea's Samsung Heavy Industries has secured an order worth approximately $2.88 billion to build the first floating LNG production unit for Delfin Midstream, the US developer of a floating LNG export project offshore Louisiana, according to shipbuilding sources.

More News Like This

Worley, Baker Hughes ink LNG pact

Australian engineering firm Worley has signed a memorandum of understanding with US energy services firm Baker Hughes to jointly pursue opportunities in the liquefied natural gas (LNG) sector.

Baker Hughes booked $1.2 billion in LNG equipment orders in Q1

US energy services firm Baker Hughes booked $1.2 billion of LNG equipment orders in the first quarter of this year, including a QatarEnergy contract for the North Field West project, according to CEO Lorenzo Simonelli.

Baker Hughes secures Argentina LNG pipeline gig

US energy services firm Baker Hughes has secured an order to supply three gas compression units for a natural gas pipeline which will deliver feed gas to Southern Energy’s two floating LNG units in Argentina.

ST LNG picks Baker Hughes tech for US floating LNG project

ST LNG has selected Baker Hughes to supply gas compression, power generation equipment, and project development support for its proposed floating liquefaction project with a capacity of up to 8.4 mtpa offshore Matagorda, Texas.