Delfin seeks more time to build its US floating LNG export project

Delfin LNG, a unit of Delfin Midstream and the developer of a floating LNG export project in the Gulf of Mexico, has requested more time from US FERC to put into service the project’s onshore facilities in Louisiana.

The firm revealed this in a letter to US FERC seeking an additional one-year extension to construct, operate and maintain certain onshore metering, compression, and piping facilities until September 2023.

The facilities would transport and deliver natural gas to Delfin’s deepwater port in federal waters offshore Louisiana.

Delfin plans to install up to four self-propelled FLNG vessels that could produce up to 13 mtpa of LNG or 1.7 billion cubic feet per day of natural gas.

This is the fourth time Delfin has asked FERC for an extension to build the facilities.

However, this request follows a $3 billion long-term deal to supply liquefied natural gas to a unit of energy trader Vitol.

Under the SPA, Delfin will supply 0.5 million tonnes per annum on a free on-board (FOB) basis at its deepwater port to Vitol for a 15-year period.

In addition to the SPA, Vitol has completed a strategic investment in the company.

Delfin seeks more time to build its US floating LNG export project
Image: Delfin LNG

Besides the Vitol deal, Delfin has entered into term sheets or heads of agreement with other LNG off-takers.

The firm told FERC it expects to finalize these deals “soon”.

In addition to this commercial progress, Delfin has completed FEED with Samsung Heavy Industries and Black & Veatch for the construction of the units. The firm has recently
conducted meetings with MARAD, and the US Coast Guard, concerning compliance with the
conditions of its deepwater port authorization as well.

As a modular project consisting of four separate floating LNG vessels, Delfin requires only 2 to 2.5 mtpa of long-term off-take contracts to support a final investment decision and begin construction of its project.

“Given all this significant progress, Delfin LNG is on schedule to make FID on its first FLNGV by the end of this year,” it said.

Most Popular

QatarEnergy CEO says damaged Ras Laffan LNG trains to take three years to repair

State-owned LNG giant QatarEnergy expects the damage to two liquefaction trains at its giant Ras Laffan complex to take three years to repair, according to Qatar’s energy minister and CEO of QatarEnergy, Saad Sherida Al-Kaabi.

Glencore pens Chinese LNG supply deal

Switzerland-based energy trader Glencore has signed a long-term deal to supply liquefied natural gas (LNG) to a unit of China Suntien Green Energy.

Equinor seals long-term LNG SPA with Thailand’s PTT

Norwegian energy firm Equinor has signed a long-term LNG sales and purchase agreement with a unit of Thailand’s PTT.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project more than 50 percent complete

Cheniere's Corpus Christi Midscale Trains 8 and 9 project in Texas is more than 50 percent complete, according to the latest construction update.

Construction progresses on Woodside’s Louisiana LNG project

Australian LNG player Woodside and its contractor Bechtel continue to advance construction of the first phase of the Louisiana LNG export terminal.

Glenfarne’s Magnolia LNG seals feed gas deal

Glenfarne’s Magnolia LNG has signed a long-term feed gas deal with Texas Eastern Transmission for its planned liquefaction and export plant in Louisiana.

Cheniere set to start LNG production at seventh Corpus Christi expansion train

US LNG exporter Cheniere is set to start LNG production at the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas following the latest approval from the US FERC.