Venture Global wins approval for final block at Calcasieu Pass LNG plant

US LNG export player Venture Global LNG has received approval from federal regulators to introduce fluids into the Block 9 liquefaction modules at its Calcasieu Pass plant in Louisiana.

The Federal Energy Regulatory Commission (FERC) said in a filing dated July 22 it had approved Venture Global’s recent request to “introduce hazardous fluids into Liquefaction Block 9”.

Prior to this, FERC gave green light to Venture Global to commission the block on July 8, according to a separate filling.

With this, Venture Global received approvals to commission all the 18 modular units configured in 9 blocks.

Following completion later this year, the project will have a capacity to produce 10 mtpa of LNG or 1.3 billion cubic feet per day (Bcf/d).

Venture Global already won approval from FERC to place in service the first four liquefaction blocks.

Earlier this month, the firm asked the regulator to put in service the fifth and the sixth liquefaction blocks at its Calcasieu Pass plant.

Since the first commissioning cargo in March, most of the Calcasieu Pass shipments landed in Europe due to high prices and as European countries look to reduce reliance on Russian gas supplies.

The Calcasieu Pass project is the seventh US liquefaction and export facility to begin producing LNG since 2016.

It receives its feedgas through Venture Global’s TransCameron pipeline, which has interconnections with the ANR, TETCO, and Bridgeline pipelines.

Calcasieu Pass has contracts with Shell, BP, Edison, Galp, Repsol, PGNiG, Sinopec’s unit Unipec, and CNOOC.

Most Popular

BP, partners take FID on $7 billion Tangguh UCC project

BP said in a statement on Thursday the Tangguh Ubadari, CCUS, compression project (UCC) has the potential to unlock...

CoolCo seeks long-term employment for two LNG carriers

In August, Coolco said it plans to employ its first newbuild LNG vessel, Kool Tiger, on a shorter deal...

LNG Canada pipeline enters commercial service

Canada's TC Energy said on Tuesday CGL had executed a commercial agreement with LNG Canada and CGL customers that...

More News Like This

Venture Global’s Plaquemines LNG to introduce hazardous fluids to first block

The regulator said on Thursday it had granted Venture Global Plaquemines LNG to commission and introduce hazardous fluids to...

Venture Global’s vessel arrives at Plaquemines LNG plant

The 174,000-cbm LNG carrier was on Tuesday located at the LNG plant along the Mississippi River, according to its...

BP, Venture Global to supply LNG to Bulgargaz in January and February

Bulgargaz previously sought two LNG cargoes for delivery during January and February 2025. The company recently announced that 19 international...

Venture Global nears launch of Plaquemines LNG production

According to a FERC filing, Plaquemines LNG has now fulfilled the environmental conditions which were necessary prior to the...