Tellurian updates on Driftwood LNG early works

US LNG firm Tellurian and compatriot engineering and construction giant Bechtel are moving forward with site preparation works for the Driftwood LNG export project in Louisiana.

In March, Tellurian issued a limited notice to proceed to Bechtel under its executed EPC contract to begin construction of phase one of the Driftwood LNG plant.

Tellurian is still working to complete financing for the project worth about $12.8 billion.

Phase one will include two LNG plants near Lake Charles with an export capacity of up to 11 million tonnes per annum (mtpa).

The LNG terminal developer said in its July construction report sent to US FERC that the project continued activities under the LNTP scope.

These include site preparation, concrete pile driving, offloading of concrete pile shipments,
mobilization of construction equipment and tools, and preparations to commence
concrete crushing scheduled for August, according to the update.

Tellurian updates on Driftwood LNG early works
Pile laydown area (Image: Tellurian)

In addition, Driftwood LNG continued the construction of the water wells as a non-jurisdictional activity under the early works program, it said.

In August, Tellurian and Bechtel will continue mobilizing professional staff and craft professionals and will continue demolition of building foundations and underground utilities.

They will also start stripping and site preparation in the LNG tanks area as well as begin receiving rebar for permanent plant foundations.

Tellurian’s co-founder and executive chairman, Charif Souki, said in June that the firm invested $750 million in its Driftwood project in Louisiana up to date.

He said the firm committed to spend another $250 million with Bechtel for Driftwood for the rest of of the year.

Souki also said that Tellurian “is still on schedule” to deliver LNG in the first quarter of 2026, adding that the financing “will fall into in place in the proper order”.

Most Popular

Nakilat says no one injured after LNG carrier attack

Qatari LNG shipping giant Nakilat said that no one was injured after its 266,000-cbm Q-Max LNG carrier Al Mayeda was hit by "unidentified objects" while transiting the Arabian Gulf on Friday evening.

ExxonMobil boosts Rovuma LNG stake

US energy giant ExxonMobil has increased its stake in the planned Rovuma LNG project in Mozambique through a deal with Italy's Eni, while the company still targets a final investment decision by the end of this year, according to ExxonMobil CEO Darren Woods.

Technip Energies ready to hand over first NFE LNG train to QatarEnergy

French LNG engineer Technip Energies is ready to hand over the first train of the North Field East LNG project in Qatar to state-owned LNG giant QatarEnergy, while the second train has already started commissioning, according to Technip Energies CEO Arnaud Pieton.

More News Like This

Construction progresses on Woodside’s Louisiana LNG project

Australian LNG player Woodside and its contractor Bechtel continue to advance construction of the first phase of the Louisiana LNG export terminal.

Baker Hughes scores equipment and services contracts for Cheniere’s Sabine Pass LNG terminal

US energy services firm Baker Hughes said it had secured three "substantial" awards for Cheniere’s Sabine Pass LNG export facility in Cameron Parish, Louisiana.

Cheniere, Bechtel seal EPC deal for first Sabine Pass LNG expansion phase

A unit of Cheniere Energy Partners has entered into a lump sum, turnkey, engineering, procurement, and construction (EPC) contract with Bechtel for the first phase of the Sabine Pass LNG expansion project in Louisiana. In addition, Bechtel has received a limited notice to proceed to start early engineering and procurement for the project.

Woodside awards Louisiana LNG tugboat contract

Australian LNG player Woodside has awarded a services contract to Green Tug Towing, a joint venture of Harbor Docking & Towing and Saltchuk Marine, for the design and construction of four new tugs to be built at C&C Marine and Repair in Louisiana, and delivered to Louisiana LNG in 2028.