Gasunie says to welcome both FSRUs in Eemshaven next week

Dutch gas grid and LNG terminal operator, Gasunie, is expecting its two chartered floating storage and regasification units to arrive by September 7 at the new LNG import hub in Eemshaven.

EemsEnergyTerminal, the first FSRU-based facility in the Netherlands, is being prepared in record time so it can welcome the two units, as the Netherlands and other European countries such as Germany look to slash reliance on Russian pipeline gas and boost energy security.

In March this year, Belgium’s Exmar and Gasunie signed a five-year charter deal for the 120 meters long 26,000-cbm FSRU S188.

Following a trip from Singapore, this barge-based FSRU arrived in Rotterdam in June for modification works at the Damen yard.

In the meantime, Exmar also renamed this unit Eeemshaven LNG.

Besides this FSRU, Gasunie also signed a charter deal for a larger FSRU with US LNG player New Fortress Energy. The vessel in question is the 170,000-cbm Golar Igloo.

Golar Igloo arrived in Rotterdam from Denmark last week, its AIS data shows.

Gasunie to host event in Eemshaven on September 8

A spokeswoman for Gasunie told LNG Prime via email that the FSRU Golar Igloo would arrive on September 4 at about 17.20h local time in Groningen province’s Eemshaven port.

As per the FSRU Eemshaven LNG, it would probably arrive on September 7 in Eemshaven, the spokeswoman said.

Also, Gasunie would hold an official ceremony to welcome the two FSRUs on September 8, attended by officials from Gasunie, the Czech Prime Minister, and others, the spokeswoman said.

The state-owned firm previously said it expects first delivery of LNG through the terminal to take place in mid-September.

The spokeswoman did not provide any additional information regarding the first shipment.

To remind, LNG giant Shell booked 4 bcm while Czech firm ČEZ took 3 bcm of the terminal’s total capacity. France’s Engie secured the remaining 1 bcm of capacity.

The Eemshaven hub is the second LNG import facility in the Netherlands after the Gate terminal in Rotterdam, which is owned by Gasunie and Vopak.

With an expansion at the Gate terminal in Rotterdam and the Eemshaven project, Dutch capacity will double from current 12 bcm to 24 bcm.

Most Popular

TotalEnergies to transfer Papua LNG operatorship to ExxonMobil

French energy giant TotalEnergies said on Monday that Papua LNG has achieved "major" contractual and commercial milestones, marking "decisive" steps towards a final investment decision. These include completing the EPC tendering process and transferring Papua LNG operatorship to US energy giant ExxonMobil, operator of the PNG LNG project.

Arctic LNG 2 seeks $1 billion from Hanwha Ocean over terminated LNG carrier orders

Novatek-led Arctic LNG 2 is seeking approximately $1 billion in damages from South Korean shipbuilder Hanwha Ocean over terminated shipbuilding contracts for Arc7 ice-class LNG tankers.

Gasunie, Vopak plan fifth Gate LNG jetty

Dutch partners Gasunie and Vopak plan to build a fifth liquefied natural gas (LNG) jetty at their Gate terminal in the port of Rotterdam.

More News Like This

Gasunie, Vopak plan fifth Gate LNG jetty

Dutch partners Gasunie and Vopak plan to build a fifth liquefied natural gas (LNG) jetty at their Gate terminal in the port of Rotterdam.

Exmar in $150 million bond issue

Belgian shipping firm Exmar said it had placed $150 million in new senior unsecured bonds to fund growth.

Gasunie: Dutch gas storage will not meet winter filling target

Dutch gas grid and LNG terminal operator Gasunie said on Wednesday that the Netherlands will not meet its previously set gas storage filling target of 115 TWh for this winter, which is about half of the country's gas consumption.

Exmar working on new LNG projects

Belgian shipping firm Exmar is actively pursuing new LNG import and floating liquefaction projects after winning three awards over the past year.