BP’s third Tangguh LNG train nearing completion

BP’s Train 3 project at the Tangguh LNG facility in Indonesia is nearing completion and is still expected to start operations next year.

Operator BP and its partners are expanding the 7.6 mtpa facility in Papua Barat province with the addition of the third liquefaction train with a capacity of 3.8 mtpa.

Besides the expansion, BP is also working on a carbon capture utilization and storage project at the facility.

BP and the Chiyoda-Saipem-Tripatra-Suluh Ardhi Engineering (CSTS) consortium, the project’s EPC contractor, originally expected to launch the expansion project in the third quarter of 2020.

However, BP delayed the launch of the project several times due to the Covid-19 pandemic.

Earlier this year, BP’s chief executive Bernard Looney said during the company’s second-quarter results call that BP hopes to start the third train by the end of next year.

BP did not provide any updates regarding the project in its third-quarter results, but Chiyoda confirmed in its recent quarterly report that the project would go online next year.

“Construction is in the final stage and is approaching completion,” Chiyoda said.

Recent local media reports said, citing Indonesia’s regulator SKK Migas, that the project has entered into the commissioning stage and that it could enter into operation in the first quarter of the next year.

BP Berau and its affiliates in Indonesia hold a 40.22 percent interest in the Tangguh project.

Other Tangguh production sharing contract partners are MI Berau, CNOOC Muturi, Nippon Oil Exploration, KG Berau Petroleum, Indonesia Natural Gas Resources Muturi, and KG Wiriagar Petroleum.

Most Popular

CoolCo seeks long-term employment for two LNG carriers

In August, Coolco said it plans to employ its first newbuild LNG vessel, Kool Tiger, on a shorter deal...

BP, partners take FID on $7 billion Tangguh UCC project

BP said in a statement on Thursday the Tangguh Ubadari, CCUS, compression project (UCC) has the potential to unlock...

LNG Canada pipeline enters commercial service

Canada's TC Energy said on Tuesday CGL had executed a commercial agreement with LNG Canada and CGL customers that...

More News Like This

BP, partners take FID on $7 billion Tangguh UCC project

BP said in a statement on Thursday the Tangguh Ubadari, CCUS, compression project (UCC) has the potential to unlock...

BP, Venture Global to supply LNG to Bulgargaz in January and February

Bulgargaz previously sought two LNG cargoes for delivery during January and February 2025. The company recently announced that 19 international...

Kosmos: Tortue FLNG to start production at end of fourth quarter

In February, the 2.5 mtpa FLNG, which was converted from a 1975-built Moss LNG carrier with a storage...

Kotug clinches Tortue FLNG gig

Kotog said in a statement on Thursday that the contract award follows a "thorough and competitive" tender process. KOTUG will...