Freeport LNG pushes back restart to January

Freeport LNG, the operator of the three-train 15 mtpa liquefaction plant, is now expecting to restart operations at its facility in Texas in January.

The LNG terminal operator closed the liquefaction and export facility some six months ago following an incident that took place on June 8.

Earlier this month, Freeport LNG again delayed the restart of the plant targeting initial production at the facility by the end of this year.

Freeport LNG said in a update on Friday that it continues to make “notable progress” on its path towards the restart of liquefaction operations.

“As of December 23rd, the reconstruction work necessary to commence initial operations is substantially complete, and the company is submitting responses to the last remaining questions included in the Federal Energy Regulatory Commission’s December 12 data request,” it said.

“Given the time needed for the regulatory agencies to review the company’s responses and to seek any necessary clarification, Freeport LNG now does not anticipate commencing the initial restart of its liquefaction facility until the second half of January 2023,” the LNG terminal operator said.

BP, Jera, Osaka Gas, SK E&S, as well as TotalEnergies have long-term contracts with Freeport LNG.

Besides the three trains, Freeport LNG is also planning to add another production unit with a capacity of 5 mtpa, but it has not yet taken a final investment decision.

In October, US energy regulators granted Freeport LNG’s request for a 26-month extension of time to build the fourth liquefaction train.

Most Popular

Atlantic spot LNG rates drop below $80,000 per day

Atlantic spot LNG shipping rates continued to drop this week, decreasing below $80,000 per day, according to Spark Commodities.

MISC orders LNG vessel for charter to Petronas

Malaysian LNG shipping firm MISC has ordered one 18,700-cbm LNG carrier from China's Hudong-Zhonghua, backed by a 10-year charter deal with a unit of its parent Petronas.

Woodside achieves first Scarborough gas

Australian LNG player Woodside said on Wednesday that it achieved first gas from the Scarborough reservoir, as the company continues to target first LNG cargo in the fourth quarter this year.
spot_img

More News Like This

Atlantic spot LNG rates drop below $80,000 per day

Atlantic spot LNG shipping rates continued to drop this week, decreasing below $80,000 per day, according to Spark Commodities.

US weekly LNG exports reach 35 cargoes

US liquefied natural gas (LNG) plants sent 35 cargoes during the week ending July 29, one cargo more than the week before, according to the Energy Information Administration.

Netherlands was top destination for US LNG in May

LNG import terminals in the Netherlands were the top destinations for US liquefied natural gas cargoes in May this year, according to the Department of Energy’s LNG monthly report.

Atlantic LNG shipping rates decrease this week

Atlantic spot LNG shipping rates dropped this week, while Pacific rates were flat compared to the week before, according to Spark Commodities.