LNG Canada pipeline more than 81 percent complete

TC Energy’s Coastal GasLink is moving forward with works on the giant pipeline that will supply natural gas to the Shell-led LNG Canada export terminal, as it enters the final year of construction.

Coastal GasLink said in a construction update last week that the overall progress on the project had reached 81.2 percent completion as of the end of November.

Some of the most notable achievements this year include the 100 percent pipe install in sections 1 and 4, the completion of the Wilde Lake compressor station, and the start of pipe install at Cable Crane Hill, which has reached 45 percent pipe install ahead of schedule, it said.

To date, Coastal GasLink has installed more than 490 km of pipe across the 670-km route, according to the firm.

“Overall, our team has spent more than 38 million hours working on this project, with more than 6,000 women and men employed at our peak,” the firm said.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023 but the costs will significantly rise.

In July, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said in November that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

As per the LNG Canada plant in Kitimat, the project is more than 70 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Vopak moving forward with permitting process for Australian LNG import project

Dutch independent storage tank firm Vopak is moving forward with the permitting process for its planned FSRU-based LNG import facility in Australia’s Victoria state, according to CEO Dick Richelle.

Excelerate seals Bahamas LNG deal

US FSRU player Excelerate has signed an 11-year LNG supply agreement with AxDo, a joint venture between Axpo and Bahamas-based energy and maritime logistics company Domicisle LNG, supporting development of the Bahamas LNG hub.

Worley clinches EPC gig for Venture Global’s CP2 LNG expansion project

Australian engineering firm Worley has signed a reimbursable engineering, procurement, and construction (EPC) contract for Venture Global’s CP2 LNG expansion project in Louisiana.

More News Like This

Yokogawa bags LNG Canada Phase 2 gig

A unit of Japanese engineering firm Yokogawa has secured a contract from a joint venture of US engineer Fluor and Japan’s JGC to serve as the main automation contractor for the Shell-led LNG Canada Phase 2 project in Kitimat, British Columbia.

Blackstone-led group buys LNG Canada stake from Mitsubishi

A group led by US-based private equity firm Blackstone has agreed to invest $3.1 billion to acquire a 49.9 percent non-controlling interest in a Mitsubishi subsidiary that holds an interest in the Shell-led LNG Canada project.

Japan’s Kyushu Electric inks LNG Canada deal

Japan’s Kyushu Electric Power has signed a basic agreement with Diamond Global Energy, a unit of Mitsubishi, to buy liquefied natural gas (LNG) from the second phase of the Shell-led LNG Canada project in Kitimat.

Canada backs Fort Simpson LNG power plant

The government of Canada is backing the construction of NTPC's new power plant in Fort Simpson that will primarily generate power using liquefied natural gas (LNG).