LNG Canada pipeline more than 81 percent complete

TC Energy’s Coastal GasLink is moving forward with works on the giant pipeline that will supply natural gas to the Shell-led LNG Canada export terminal, as it enters the final year of construction.

Coastal GasLink said in a construction update last week that the overall progress on the project had reached 81.2 percent completion as of the end of November.

Some of the most notable achievements this year include the 100 percent pipe install in sections 1 and 4, the completion of the Wilde Lake compressor station, and the start of pipe install at Cable Crane Hill, which has reached 45 percent pipe install ahead of schedule, it said.

To date, Coastal GasLink has installed more than 490 km of pipe across the 670-km route, according to the firm.

“Overall, our team has spent more than 38 million hours working on this project, with more than 6,000 women and men employed at our peak,” the firm said.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023 but the costs will significantly rise.

In July, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said in November that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

As per the LNG Canada plant in Kitimat, the project is more than 70 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Technip Energies wins contract for Eni’s Coral Norte FLNG

France-based LNG engineering giant Technip Energies has won a contract for preliminary work on Eni's second FLNG project in Mozambique, Coral Norte (Coral North).

Victrol: LNG London hits bunkering milestone

The Shell-chartered inland bunkering vessel LNG London, owned by a joint venture of Belgium's Victrol and France's Sogestran, has reached a new operational milestone.

Himalaya’s LNG-fueled bulkers earned $34,500 per day in June

LNG-powered bulker owner Himalaya Shipping achieved average time charter equivalent earnings of about $34,500 per day in June.

More News Like This

LNG Canada sends second cargo

Shell-led LNG Canada has shipped the second cargo of liquefied natural gas from its Kitimat facility on the west coast of Canada. LNG Canada shareholder Petronas will deliver this shipment to Japan.

Shell’s LNG Canada to ship second cargo

Shell-led LNG Canada is expected to soon ship the second cargo of liquefied natural gas from the Kitimat facility on the west coast of Canada, according to shipping data.

Shell ships first LNG Canada cargo

LNG giant Shell and its partners have shipped the first cargo produced at the LNG Canada facility in Kitimat, on the west coast of Canada.

LNG carrier arrives to load first LNG Canada cargo

The 174,000-cbm GasLog Glasgow has arrived at the LNG Canada jetty in Kitimat to load the first LNG cargo produced at the Shell-led terminal, an LNG Canada spokesperson told LNG Prime on Saturday.