LNG Canada pipeline more than 81 percent complete

TC Energy’s Coastal GasLink is moving forward with works on the giant pipeline that will supply natural gas to the Shell-led LNG Canada export terminal, as it enters the final year of construction.

Coastal GasLink said in a construction update last week that the overall progress on the project had reached 81.2 percent completion as of the end of November.

Some of the most notable achievements this year include the 100 percent pipe install in sections 1 and 4, the completion of the Wilde Lake compressor station, and the start of pipe install at Cable Crane Hill, which has reached 45 percent pipe install ahead of schedule, it said.

To date, Coastal GasLink has installed more than 490 km of pipe across the 670-km route, according to the firm.

“Overall, our team has spent more than 38 million hours working on this project, with more than 6,000 women and men employed at our peak,” the firm said.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023 but the costs will significantly rise.

In July, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said in November that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

As per the LNG Canada plant in Kitimat, the project is more than 70 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Delfin takes FID on first FLNG

Delfin Midstream has taken a final investment decision for the first 4.4 mtpa floating liquefied natural gas unit of its LNG project under development in Louisiana. Delfin says the FLNG is the first floating liquefaction facility in the United States and the world's largest FLNG.

Malaysia’s Petronas Gas, Integrax ink pact for new LNG import terminal

Malaysia's Petronas Gas, a unit of Petronas, has signed a binding deal with compatriot Integrax, a part of TNB Power Generation, to jointly develop the country's first FSRU-based LNG import terminal in Lumut, Perak.

Samsung Heavy secures FLNG order from Delfin

South Korea's Samsung Heavy Industries has secured an order worth approximately $2.88 billion to build the first floating LNG production unit for Delfin Midstream, the US developer of a floating LNG export project offshore Louisiana, according to shipbuilding sources.

More News Like This

Fluor, JGC get limited notice to proceed for LNG Canada expansion

Fluor, JGC get limited notice to proceed for LNG Canada expansion

U-Ming, K Line name LNG carrier in South Korea

Taiwan’s shipowner U-Ming Marine Transport has named the first liquefied natural gas (LNG) carrier in its fleet as part of a joint venture with Japan's shipping giant K Line.

Shell’s LNG Canada eyes Phase 2 FID by end of this year

Shell-led LNG Canada has reached a deal with the provincial and state governments to work towards a final investment decision on the planned expansion of its Kitimat LNG export facility on the west coast of Canada by the end of this year.

Shell to buy Canada’s ARC Resources in $16.4 billion deal

UK-based LNG giant Shell has agreed to acquire Canadian gas producer ARC Resources in a deal valued at approximately $16.4 bilion, including debt. Shell said ARC’s proved plus probable gas reserves have the potential to support its LNG growth in Canada.