TotalEnergies assessing Mozambique LNG restart

France’s TotalEnergies is working to restart construction on its $20 billion Mozambique LNG project after declaring force majeure some two years ago due to new attacks in Cabo Delgado province.

TotalEnergies declared force majeure on the giant LNG project in April 2021 and withdrew all personnel from the site.

In February last year, TotalEnergies CEO Patrick Pouyanne said the company would not restart work on the LNG project until the civil population comes back to Cabo Delgado province where the Afungi site is located.

Pouyanne visited the province last week and met with Mozambique’s President Filipe Nyusi to discuss the security and humanitarian situation in Cabo Delgado province, according to a statement by the French energy giant.

Independent mission

During this visit, Pouyanne entrusted Jean-Christophe Rufin, an expert in humanitarian action and human rights, with an independent mission to assess the humanitarian situation in Cabo Delgado province, according to the statement.

This mission will also evaluate the actions taken by Mozambique LNG and will propose any additional actions to be implemented, if required, it said.

TotalEnergies said that the report of this mission will be delivered at the end of February and its conclusions will be shared with all Mozambique LNG’s partners, who shall decide whether the conditions are met for resuming project activities.

Situation improved “significantly”

“Since 2021, the situation in Cabo Delgado province has improved significantly, thanks in particular to the support provided by the African countries that committed themselves to restore peace and security,” Pouyanne said in the statement.

“The lifting of the force majeure and the resumption of activities at the Mozambique LNG project site require, in particular the restoration of security in the region, the resumption of public services and the return to normal life for the people of the region,” he said.

TotalEnergies had previously planned to launch the project in 2024. Mozambique LNG includes the development of offshore gas fields in Mozambique’s Area 1 and a 13.1 mtpa liquefaction plant at the Afungi complex.

The project will also have a fleet of dedicated LNG carriers.

Besides TotalEnergies, other partners in the project are Japan’s Mitsui, Mozambique’s ENH, Thailand’s PTT, and Indian firms ONGC, Bharat Petroleum, and Oil India.

The project’s EPC contractor is CCS JV, a venture between Saipem, McDermott, and Chiyoda.

Mozambique LNG is the first onshore LNG plant in the country.

The country became an LNG exporter in November last year after Eni’s Coral Sul FLNG located offshore Mozambique shipped its first cargo of LNG.

Most Popular

Venture Global’s Plaquemines LNG seals new gas supply deal

Venture Global LNG’s Plaquemines LNG has signed a new natural gas sale and purchase deal with gas marketer Tenaska Marketing Ventures, according to a DOE filing.

TotalEnergies working on Mozambique LNG restart, CEO says

France's TotalEnergies and its partners in the giant Mozambique LNG project are still working with the Mozambique government on restarting construction on the 12.8 mtpa project, according to Patrick Pouyanne, CEO of TotalEnergies.

US LNG exports down to 28 cargoes

US liquefied natural gas (LNG) plants shipped 28 cargoes during the week ending July 23. According to the Energy Information Administration, pipeline deliveries to the LNG terminals decreased compared to the prior week.

More News Like This

TotalEnergies working on Mozambique LNG restart, CEO says

France's TotalEnergies and its partners in the giant Mozambique LNG project are still working with the Mozambique government on restarting construction on the 12.8 mtpa project, according to Patrick Pouyanne, CEO of TotalEnergies.

TotalEnergies reports higher LNG sales, lower earnings

French energy giant TotalEnergies reported higher LNG sales in the second quarter of this year, while its integrated LNG business logged lower adjusted net operating income due to lower prices.

TotalEnergies, CMA CGM to launch LNG bunkering JV

French energy giant TotalEnergies and compatriot shipping firm CMA CGM have signed a deal to develop a 50/50 logistics joint venture dedicated to the implementation and operation of an LNG bunkering supply solution at the Dutch port of Rotterdam.

Cameron LNG hits new milestone

Sempra Infrastructure, a unit of Sempra, and its partners have shipped the 1,000th cargo of liquefied natural gas from the Cameron LNG export plant in Louisiana since 2019.