Sempra expects to take FID on Port Arthur LNG in March

US LNG player Sempra Infrastructure, a unit of Sempra, is expecting to take a final investment decision on the first phase of its proposed Port Arthur LNG project in Texas by the end of March.

The first phase of the Port Arthur LNG project will have two trains with a total capacity of about 13.5 million tonnes per annum and two storage tanks with a capacity of 160,000 cbm.

Sempra Infrastructure previously entered into long-term agreements with each of ConocoPhillips, Ineos, Engie, RWE, and the most recent with PKN Orlen.

The first phase of the project is fully subscribed with 10.5 Mtpa under binding long-term agreements.

Besides taking volumes, ConocoPhillips would acquire a 30 percent ownership interest in Port Arthur LNG Phase 1 as well.

In October last year, Sempra Energy announced that it finalized its fixed-price engineering, procurement and construction (EPC) contract for Port Arthur LNG Phase 1 with engineering anf construction giant Bechtel.

The two firms amended and restated the fixed-price contract which is now worth about $10.5 billion.

One or more investors

Justin Bird, CEO of Sempra infrastructure, said during Sempra’s 2022 earnings call on Tuesday that the company has completed the marketing phase for Port Arthur LNG Phase 1.

He confirmed that the firm is still targeting FID by the end of the first quarter.

“We have carefully structured this development project to reduce risk by fully contracting the long-term offtake securing a fixed price EPC and identifying world-class development partners,” he said.

With the completion of marketing and execution of the EPC contract, the company is now focused on finalizing the project level debt as well as equity financing.

“On the basis of the current financing efforts that are underway, we aim to efficiently raise lower-cost capital and protect Sempra Infrastructure’s investment-grade balance sheet,” he said.

“We are targeting Sempra Infrastructure Partners’ ownership in the project of between 20 percent and 30 percent with ConocoPhillips owning 30 percent and the balance being sold in the form of a non-controlling interest to one or more investors,” he said.

Second phase

Besides the first phase of the Port Arthur LNG project, Sempra Infrastructure is also working on the second phase of the project.

Port Arthur LNG’s expansion project would add two more liquefaction trains capable of producing about 13.5 mtpa.

Looking past the first phase of Port Arthur LNG and the second phase of the Cameron LNG project, Bird said during the call that “there is a lot of excitement around a second phase at Port Arthur.”

“We have MOUs for volumes out of Phase 2 and are discussions with many parties to fill any outstanding volumes,” he said.

“If you ask me the pecking order, I think the second phase at Port Arthur would be next,” he said.

Most Popular

Delfin takes FID on first FLNG

Delfin Midstream has taken a final investment decision for the first 4.4 mtpa floating liquefied natural gas unit of its LNG project under development in Louisiana. Delfin says the FLNG is the first floating liquefaction facility in the United States and the world's largest FLNG.

Malaysia’s Petronas Gas, Integrax ink pact for new LNG import terminal

Malaysia's Petronas Gas, a unit of Petronas, has signed a binding deal with compatriot Integrax, a part of TNB Power Generation, to jointly develop the country's first FSRU-based LNG import terminal in Lumut, Perak.

Samsung Heavy secures FLNG order from Delfin

South Korea's Samsung Heavy Industries has secured an order worth approximately $2.88 billion to build the first floating LNG production unit for Delfin Midstream, the US developer of a floating LNG export project offshore Louisiana, according to shipbuilding sources.

More News Like This

Sempra’s ECA LNG kicks off LNG production

US LNG exporter Sempra has started producing LNG at the first phase of its Energia Costa Azul LNG export terminal in Mexico.

Sempra’s Port Arthur LNG seeks approval for cooldown cargoes

Sempra's Port Arthur LNG is seeking approval from the US Department of Energy to receive cooldown cargoes and re-export LNG from its Texas facility as part of the commissioning process.

Sempra’s ECA LNG to kick off LNG production in June

US LNG exporter Sempra still expects to start producing LNG at the first phase of its Energia Costa Azul LNG export terminal in Mexico in June, according to Sempra's management.

Construction advances on Port Arthur LNG terminal

US LNG exporter Sempra Infrastructure, a unit of Sempra, and compatriot Bechtel continue to make progress on the construction of the Port Arthur LNG export terminal in Texas.