LNG Canada’s new tug berth to be completed in early 2024

A new tug berth being built for the Shell-led LNG Canada export project will be ready in early 2024 to welcome a fleet of dual-fuel and electric tugs.

Construction of the tug berth facility started in early 2023 and is scheduled to be fully completed in early 2024, LNG Canada said in a statement issued last week.

Bridgemans Kitamaat Joint Venture, a Haisla Nation partnership, has secured the new engineering, procurement, and construction contract award which includes the installation of marine piles, floating docks, and a breakwater.

LNG Canada says the new tug berth is essential to operation of the escort tugs and harbor tugs that will provide ship-assist and escort towing services to LNG carriers calling at LNG Canada’s export facility.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

LNG Canada's new tug berth to be completed in early 2024
Image: LNG Canada

HaiSea Marine, majority-owned by the Haisla Nation in partnership with Canada’s Seaspan ULC, has a major contract with LNG Canada to build and operate escort and harbor tugs required for the LNG export project worth more than $30 billion.

The new fleet of tugs will consist of two RAstar 4000-DF escort dual-fuel tugs that will run on LNG and also diesel.

Moreover, the fleet also includes three ElectRA 2800 electric tugs.

Turkey’s Sanmar is building the tugs designed by Vancouver BC-based naval architect company, Robert Allan.

Earlier this year, Sanmar launched the first of two LNG dual-fuel tugs that will feature Wartsila engines.

Also, Norway’s Corvus Energy won a contract to deliver batteries to the three electric tugs.

Most Popular

Venture Global’s Plaquemines LNG seals new gas supply deal

Venture Global LNG’s Plaquemines LNG has signed a new natural gas sale and purchase deal with gas marketer Tenaska Marketing Ventures, according to a DOE filing.

TotalEnergies working on Mozambique LNG restart, CEO says

France's TotalEnergies and its partners in the giant Mozambique LNG project are still working with the Mozambique government on restarting construction on the 12.8 mtpa project, according to Patrick Pouyanne, CEO of TotalEnergies.

Yangzijiang wraps up roof raising on two LNG storage tanks

Chinese private shipyard Yangzijiang Shipbuilding has completed raising the roofs on two LNG storage tanks at its Yangzi Jiasheng terminal.

More News Like This

Shell takes FID on Egypt gas project

A unit of UK-based LNG giant Shell has taken the final investment decision for the development of the Mina West gas discovery in Egypt’s Mediterranean Sea.

South Korea gets first LNG Canada cargo

The 174,000-cbm GasLog Glasgow, which is carrying the first liquefied natural gas cargo produced at the Shell-led LNG Canada facility in Kitimat, has arrived in Tongyeong, South Korea, according to shipping data.

LNG Canada to send third cargo

Shell-led LNG Canada is expected to soon ship the third cargo of liquefied natural gas from the Kitimat facility, according to shipping data.

Victrol: LNG London hits bunkering milestone

The Shell-chartered inland bunkering vessel LNG London, owned by a joint venture of Belgium's Victrol and France's Sogestran, has reached a new operational milestone.