LNG Canada pipeline more than 85 percent complete

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, is more than 85 percent complete and recently reached a new milestone.

Coastal GasLink said in a construction update that the overall progress on the project reached 85.5 percent completion as of the end of February.

There were 5,489 workers employed across the project route as of February 28.

Last month, TC Energy said that the pipeline was 84 percent complete, while the firm is also evaluating the second phase of the project.

The Canadian firm now estimates costs for the first phase of its giant 670 kilometers long pipeline to reach C$14.5 billion ($10.7 billion).

First gas

According to Coastal GasLink, the Wilde Lake Compressor station, which serves as the starting point for the natural gas pipeline, is now introducing natural gas into the system as part of the transition to operations.

“As the project surpasses 85 percent completion, this is a significant milestone that brings Coastal GasLink one step closer to delivering critical Canadian LNG to world markets,” it said.

The Wilde Lake facility consists of three compressor units and four meter stations.

Moreover, the meter stations receive and measure the incoming gas from Coastal GasLink’s customers, and the compressor units then compresses the gas to provide the pressure required to deliver the gas 670 kilometers to LNG Canada’s site in Kitimat.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023.

LNG Canada pipeline more than 85 percent complete
Wilde Lake compressor station (Image: Coastal GasLink)

As per the LNG Canada plant in Kitimat, the project built by JGC Fluor is more than 70 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Atlantic LNG shipping rates decrease this week

Atlantic spot LNG shipping rates dropped this week, while Pacific rates were flat compared to the week before, according to Spark Commodities.

Stabilis secures new approval for Galveston LNG project

Houston-based small-scale LNG player Stabilis Solutions has received a letter of recommendation (LOR) from the US Coast Guard for its planned Galveston liquefaction facility.

Russian LNG production up 10.7 percent in January-June

Russian liquefied natural gas (LNG) production rose 10.7 percent in the first six months of this year, according to the Russian statistics agency Rosstat.
spot_img

More News Like This

LNG Canada offers option to First Nations to invest in Phase 2 storage tank

Shell-led LNG Canada has signed an agreement with five northwestern B.C. First Nations, giving them the option to invest up to C$1 billion ($711 million) to acquire an LNG storage tank slated for construction as part of the expansion of its Kitimat LNG export facility on the west coast of Canada.

LNG Canada ships 100th cargo

Shell-led LNG Canada has shipped the 100th cargo of liquefied natural gas from its Kitimat facility on the west coast of Canada.

PetroVietnam Gas receives Canadian LNG cargo

PetroVietnam Gas, a unit of state-owned PetroVietnam, has received a cargo of liquefied natural gas from Canada as it increases LNG imports amid disruptions caused by the Middle East conflict.

Fluor, JGC get limited notice to proceed for LNG Canada expansion

Fluor, JGC get limited notice to proceed for LNG Canada expansion