Cheniere seeks FERC OK to build two more Corpus Christi LNG trains

US LNG exporting giant Cheniere has filed an application with the US FERC seeking authorization to construct two midscale trains at its Corpus Christi LNG export plant in Texas.

The Corpus Christi liquefaction plant now consists of three operational trains with each having a capacity of about 5 mtpa.

In June last year, Cheniere took a final investment decision on Stage 3 expansion and officially started construction in October.

Under the expansion, Cheniere will add up to seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa, with a total production capacity of more than 10 mtpa.

Besides this expansion, Cheniere plans to build two more liquefaction trains and one storage tank as part of the third expansion phase at the plant.

Cheniere detailed the plan for the proposed Corpus Christi Liquefaction Midscale Trains 8 & 9 Project in August last year.

Majority of volumes committed

Cheniere’s units filed a formal application to build these two trains on March 30, according to a filing with FERC.

The company is asking FERC to grant this application by September 27, 2024.

Cheniere seeks FERC OK to build two more Corpus Christi LNG trains
Image: Cheniere

According to Cheniere, the project would include two trains, nearly identical in design to trains 1-7 and each capable of producing up to 1.64 mtpa of LNG, on-site refrigerant storage, a 220,000-cbm LNG storage tank, a BOG compressor, and an increase in the authorized LNG loading rate.

The project would result in an increase in the maximum marine vessel traffic from the 400
LNG carriers per year authorized at the terminal, up to 480 LNG carriers per year.

Cheniere said it would supply feed gas to the project via a combination of the previously permitted Corpus Christi Pipeline facilities and the ADCC pipeline, a non-jurisdictional intrastate pipeline designed to transport up to 1.7 Bcf/d, to be operated by WWM Operating.

Moreover, commercialization of the project “is substantially complete, with a majority of LNG export volumes from the project facilities committed via long-term LNG sales contracts,” Cheniere said.

The firm is seeking the approval from FERC by September 27, 2024 so that it may commence construction of the project in the second half of 2024.

If constructed under optimal conditions, Cheniere expects the construction to last four years.

“However, applicants are seeking authorization to complete construction and place the facilities in service by 2031 to accommodate the potential for phasing, schedule changes or other unforeseen disruptions,” it said.

Most Popular

Another steam LNG carrier sold for demolition

An NYK-managed steam liquefied natural gas (LNG) carrier has been sold for demolition, according to brokers.

Abaxx sees significant volume growth in its LNG futures

Abaxx Commodity Futures Exchange, a wholly owned subsidiary of Abaxx Technologies (CBOE:ABXX) has seen significant volume growth in its physically deliverable LNG futures during the past summer months, according to Abaxx Exchange Chief Commercial Officer Joe Raia.

Shell’s LNG Canada expansion project to get boost from government

Canadian Prime Minister Mark Carney named the planned second phase of Shell's LNG Canada export project as one of the major projects the federal government would help fast-track.

More News Like This

Cheniere clinches Botas LNG supply deal

Turkiye’s state-owned natural gas and LNG firm Botas has signed a deal to buy liquefied natural gas from US LNG exporting giant Cheniere. Botas also signed deals with SEFE, Equinor, and jera.

Golden Pass gets OK to place MP 33 compressor station in service

Golden Pass LNG, a joint venture owned by energy giants QatarEnergy and ExxonMobil, has secured approval from the US FERC to place into service its MP 33 compressor station, as it continues to move forward with commissioning activities at its three-train LNG plant in Texas.

Cheniere’s Corpus Christi expansion project almost 88 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is almost 88 percent complete, while Cheniere has also started site preparation activities for two more midscale trains.

NextDecade’s Rio Grande LNG secures final FERC approval

The US Federal Energy Regulatory Commission (FERC) has issued its final order for NextDecade's Rio Grande LNG facility and the accompanying pipeline in Texas.