Gasunie, Vopak take FID on fourth Gate LNG tank

Dutch gas grid operator Gasunie and compatriot storage tank firm Vopak have taken a final investment decision to build the fourth storage tank and add more regasification capacity at their Gate LNG terminal in the port of Rotterdam.

The expansion consists of a new LNG storage tank of 180,000 cubic meters and additional regasification capacity of 4 Bcm per year.

Gasunie and Vopak will invest about 350 million euros ($380.1 million) in this project and the two firms expect to complete the project financing by the end of 2023, according to a joint statement.

About 15 percent of the costs will be funded with equity and and 85 percent of the costs will be funded via a non-recourse project financing.

Also, the new capacity is already rented out under long-term commercial agreements and is expected to be ready for operation by the second half of 2026.

UK-based energy giant BP and a unit of PetroChina have previously agreed to book long-term capacity at the Gate LNG import terminal.

They will each acquire 2 Bcm per year of regasification and also corresponding storage capacity for a period of 20 years.

Vopak and Gasunie are the founders and owners of Gate terminal in Rotterdam which has been operational since 2011.

The terminal plays a crucial role in the supply and availability of gas in the Netherlands and its neighboring countries.

Once all planned projects at Gate terminal have been completed, the terminal will have a total regas capacity of 20 billion cubic meters per year and four LNG tanks with 720,000 cbm of storage capacity.

Increasing Dutch LNG import capacity

Hans Coenen, on behalf of the board of directors of Gasunie, said the investment in this new tank is part of a broader package of proposed and already realized measures to increase LNG import capacity in the Netherlands.

“This is necessary to compensate for the loss of Russian natural gas and to reduce the scarcity of natural gas on the European gas market,” he said.

“We are excited to build upon our successful partnership with Gasunie,” Dick Richelle, CEO at Vopak, said.

“This investment fits well with Vopak’s strategy to grow in LNG infrastructure,” he said.

The Netherlands now has two LNG import terminals with the the addition of the FSRU-based facility in the port of Eemshaven.

Gasunie, recently said that its FSRU-based LNG import facility in the port of Eemshaven has received its 50th shipment since the launch in September last year.

The company signed a deal in April with Vopak to sell 50 percent of the LNG hub which features two FSRUs.

Most Popular

CoolCo seeks long-term employment for two LNG carriers

In August, Coolco said it plans to employ its first newbuild LNG vessel, Kool Tiger, on a shorter deal...

BP, partners take FID on $7 billion Tangguh UCC project

BP said in a statement on Thursday the Tangguh Ubadari, CCUS, compression project (UCC) has the potential to unlock...

LNG Canada pipeline enters commercial service

Canada's TC Energy said on Tuesday CGL had executed a commercial agreement with LNG Canada and CGL customers that...

More News Like This

Rotterdam LNG throughput down in January-September

The port, home to Gasunie’s and Vopak’s Gate LNG import terminal, said that total LNG throughput reached 8.4 million...

Rotterdam LNG bunkering volumes continue to increase

Europe’s largest bunkering port and home of the Gate LNG import terminal reported LNG volumes of 220,120 cubic meters...

Dutch Gate gets first cargo from NFE’s Altamira LNG terminal in Mexico

The 138,000-cbm Energos Princess delivered the maiden cargo from Altamira to the LNG terminal owned by Gasunie and Vopak. Energos...

FID taken on German onshore LNG terminal

"The FID was taken within the last two weeks," a spokesman for German LNG Terminal told LNG Prime on...