LNG Canada pipeline almost 95 percent complete

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, is almost 95 percent complete.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in its latest construction update that the pipeline has achieved 94.7 percent overall completion and it still expects to complete the project by the end of 2023.

Also, the project achieved 98 percent pipe installation, while 4,820 workers were working across the project route as of August 26, it said.

As of the end of August, all 800 water crossings across the project have also been executed, including all 10 major trenchless water crossings.

LNG Canada pipeline almost 95 percent complete
Image: Coastal GasLink

While the project is quickly approaching mechanical completion at the end of 2023, there are a number of critical activities that the project team will continue to execute on, Coastal GasLink said.

These activities include clean-up and reclamation and erosion and sediment control (ESC) measures.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

LNG Canada pipeline almost 95 percent complete
Image: LNG Canada

As per the LNG Canada plant, the project built by JGC Fluor was about 85 percent complete in July and during the same month it completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

Most Popular

Petronas takes FID on Suriname FLNG project

Malaysian energy giant Petronas and Suriname’s state-owned oil and gas company Staatsolie have taken the final investment decision on the $1.6 billion Sloanea gas field development in offshore Block 52, which includes a floating liquefied natural gas (FLNG) facility.

Hudong-Zhonghua hits new LNG carrier delivery record

China’s Hudong-Zhonghua has delivered 12 large liquefied natural gas (LNG) carriers this year to date, setting a new record for the Chinese shipbuilding industry.

Shell, IRH seal LNG supply deal

IRH Global Trading, part of UAE-based IRH, has signed a term deal to buy liquefied natural gas (LNG) from a unit of UK-based LNG giant Shell.

More News Like This

Vinci scores LNG Canada tank gig

A unit of French construction company Vinci has secured a contract from a joint venture of US engineer Fluor and Japan’s JGC to build one 225,000-cbm LNG storage tank for the Shell-led LNG Canada Phase 2 project in Kitimat, British Columbia.

Yokogawa bags LNG Canada Phase 2 gig

A unit of Japanese engineering firm Yokogawa has secured a contract from a joint venture of US engineer Fluor and Japan’s JGC to serve as the main automation contractor for the Shell-led LNG Canada Phase 2 project in Kitimat, British Columbia.

Blackstone-led group buys LNG Canada stake from Mitsubishi

A group led by US-based private equity firm Blackstone has agreed to invest $3.1 billion to acquire a 49.9 percent non-controlling interest in a Mitsubishi subsidiary that holds an interest in the Shell-led LNG Canada project.

Japan’s Kyushu Electric inks LNG Canada deal

Japan’s Kyushu Electric Power has signed a basic agreement with Diamond Global Energy, a unit of Mitsubishi, to buy liquefied natural gas (LNG) from the second phase of the Shell-led LNG Canada project in Kitimat.