Freeport LNG gets OK to start commissioning second jetty

Freeport LNG, the operator of the three-train 15 mtpa liquefaction plant in Texas, has secured approval from the US FERC to start commissioning its second jetty.

In February this year, the LNG terminal operator shipped the first cargo from its LNG export plant in Texas since the shutdown in June 2022.

Freeport LNG received approvals from both FERC and PHMSA during the first quarter to restart Phase I operations.

These consist of three trains, two LNG storage tanks (tanks 1 and 2), and a single LNG jetty (dock 1).

However, these approvals did not grant Freeport LNG to commission or place LNG tank 3, loop 2, and dock 2 back into service.

In order to continue Freeport’s sequential plan to return the export facility to full commercial operations, Freeport recently requested approval from FERC for the nitrogen cooldown of the loop 2 LNG rundown piping system and the introduction of hydrocarbons to loop 2 to complete its cooldown and commissioning.

FERC said in filling dated October 27 that it has granted Freeport LNG’s request to start “commissioning, including cooldown, of Loop 2 LNG transfer piping, Dock 2, and the 8-inch LNG recirculation piping.”

The regulator said additional authorization to restart operations is necessary to reinstate service for loop 2 LNG circulation to enable ship loading to dock 2.

“Authorization will only be granted following the review of filed responses, a determination that the facilities are fit for service, and documentation that acceptable measures have been put into place to safely return the facilities to operation,” it said.

FERC also noted that Freeport LNG must also comply with any applicable PHMSA and US Coast Guard requirements.

Most Popular

Venture Global charters LNG carrier duo

Venture Global has executed two short-term charters for additional LNG tankers. The vessels were delivered in August and September 2024,...

Hudong-Zhonghua launches two LNG tankers

Chinese shipbuilder Hudong-Zhonghua has launched two 174,000-cbm liquefied natural gas (LNG) carriers. According to a statement by Hudong-Zhonghua, the launching...

Trio gets OK for $3.3 billion LNG-to-power deal in Philippines

According to separate statements by the firms, the Philippine Competition Commission (PCC) has approved the joint acquisition of two...

More News Like This

Cheniere’s Corpus Christi expansion project nears first LNG

According to a filing with the US FERC dated December 20, Corpus Christi Liquefaction requests to introduce FEED gas...

Venture Global gets OK for first Plaquemines LNG commissioning cargo

FERC granted Venture Global Plaquemines LNG's request on December 20 to "export by LNG marine vessels the volumes of...

US DOE releases LNG export study

The Biden administration said in January it will pause pending decisions on exports of LNG to non-FTA countries until DOE can...

Construction advances on Sempra’s Port Arthur LNG export terminal

In March last year, Sempra Infrastructure, a unit of Sempra, took a final investment decision for the first phase of its...