LNG Canada pipeline achieves 100 percent pipe installation

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, has achieved 100 percent pipe installation across the entire project route.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in its latest construction update that the “final ‘Golden Weld’ took place at the base of Cable Crane Hill in Section 8 West earlier this month.”

This milestone means that all 670 kilometers of pipe has been welded, coated, lowered into the trench, rigorously tested, and backfilled, it said.

“From the Wilde Lake compressor station near Dawson Creek to our metering station in Kitimat, physical construction on the project is now complete,” it said.

“The work is the last step before mechanical completion which is well on track for our year-end target and advances Coastal GasLink as Canada’s first direct path for LNG to international markets,” the firm said.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

As per the LNG Canada plant, the project built by JGC Fluor was about 85 percent complete in July and during the same month it completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

Most Popular

Atlantic and Pacific LNG rates continue to decrease

Atlantic and Pacific spot liquefied natural gas (LNG) shipping rates dropped for the second week in a row, according to Spark Commodities.

US LNG exports climb to 40 shipments

US liquefied natural gas (LNG) plants sent 40 cargoes during the week ending November 18, up three shipments from the previous week, according to the Energy Information Administration.

Cheniere’s Sabine Pass LNG expansion project gets OK from FERC

The US Federal Energy Regulatory Commission (FERC) has approved Cheniere’s planned Sabine Pass Stage 5 LNG expansion project in Louisiana.

More News Like This

Vinci scores LNG Canada tank gig

A unit of French construction company Vinci has secured a contract from a joint venture of US engineer Fluor and Japan’s JGC to build one 225,000-cbm LNG storage tank for the Shell-led LNG Canada Phase 2 project in Kitimat, British Columbia.

Yokogawa bags LNG Canada Phase 2 gig

A unit of Japanese engineering firm Yokogawa has secured a contract from a joint venture of US engineer Fluor and Japan’s JGC to serve as the main automation contractor for the Shell-led LNG Canada Phase 2 project in Kitimat, British Columbia.

Blackstone-led group buys LNG Canada stake from Mitsubishi

A group led by US-based private equity firm Blackstone has agreed to invest $3.1 billion to acquire a 49.9 percent non-controlling interest in a Mitsubishi subsidiary that holds an interest in the Shell-led LNG Canada project.

Japan’s Kyushu Electric inks LNG Canada deal

Japan’s Kyushu Electric Power has signed a basic agreement with Diamond Global Energy, a unit of Mitsubishi, to buy liquefied natural gas (LNG) from the second phase of the Shell-led LNG Canada project in Kitimat.