Sempra: Port Arthur LNG construction continues under existing permits

Sempra Infrastructure, a unit of Sempra, said it is continuing construction on the first phase of its Port Arthur LNG export project under existing permits after a US court vacated the project’s emissions permit.

The US Court of Appeals for the Fifth Circuit said in a decision dated November 14 that the Texas Commission on Environmental Quality (TCEQ) declined to impose certain emissions limits on Port Arthur LNG that it had recently imposed on another such facility, Next Decade’s Rio Grande LNG.

“In doing so, it contravened its policy of adhering to previously imposed emissions limits, but it did not adequately explain why. It therefore acted arbitrarily and capriciously under Texas law,” it said.

“Accordingly, we vacate Commission’s order granting the emissions permit at issue and remand for proceedings consistent with our opinion,” the order said.

A spokeswoman for Sempra Infrastructure told LNG Prime in an emailed statement that the company is reviewing the decision and any potential impacts it may have to the Port Arthur LNG project.

“We are continuing construction on the project under existing permits and remain committed to working with the Texas Commission on Environmental Quality and other stakeholders and are evaluating our next steps,” the spokeswoman said.

Sempra Infrastructure took a final investment decision on March 20 for the first phase of the project in Texas worth about $13 billion.

Also, the company won regulatory approval from the US FERC for the second phase of the project.

The first phase of the Port Arthur LNG project includes two trains with a total capacity of about 13 million tonnes per annum and two storage tanks with a capacity of 160,000 cbm.

The development of the proposed Phase 2 project could increase the total liquefaction capacity of the facility from some 13 mtpa to about 26 mtpa.

Sempra Infrastructure recently also completed the sale of a 42 percent non-controlling interest in its Port Arthur LNG Phase 1 project to compatriot private equity firm KKR.

Sempra Infrastructure has a controlling 28 percent indirect interest in Phase 1 at the project level, and ConocoPhillips owns the remaining 30 percent interest.

US engineering and construction giant Bechtel won the EPC contract for the first phase of the project.

Sempra Infrastructure’s unit Port Arthur LNG said in a recent monthly status report filed with FERC that construction-related activities included site clearing, grubbing, stripping, soil stabilization activities, dredging, piling, and maintenance of ECD’s.

Most Popular

Excelerate buys GasLog LNG carrier

US FSRU player Excelerate Energy has purchased a 2007-built steam liquefied natural gas (LNG) carrier from GasLog Partners, a part of Greek LNG shipping firm GasLog, according to brokers.

NextDecade, Bechtel agree $9 billion EPC deals for two Rio Grande LNG trains

US LNG firm NextDecade and compatriot Bechtel have finalized EPC contracts worth $9.09 billion for the construction of the fourth and fifth trains and related infrastructure at the Rio Grande LNG facility in Texas.

Venture Global gets FERC OK to boost Calcasieu Pass LNG capacity

US LNG exporter Venture Global LNG has received approval from the US FERC to increase the peak liquefaction capacity of its Calcasieu Pass LNG terminal in Louisiana.

More News Like This

Japan’s Jera seals US LNG supply deals

Japan's power firm and LNG trader Jera has signed 20-year agreements to buy up to 5.5 million tonnes per year of LNG from the United States. The deals include an SPA with Commonwealth LNG and the previously announced SPA with NextDecade, as well as heads of agreements with Sempra Infrastructure and Cheniere.

Sempra advances Port Arthur LNG construction

US LNG exporter Sempra and compatriot Bechtel continue to make progress with construction work on the first phase of the Port Arthur LNG export terminal in Texas.

Sempra gets non-FTA approval for Port Arthur LNG expansion

Sempra Infrastructure, a unit of Sempra, has received non-FTA approval from the US Department of Energy for the second phase of its Port Arthur LNG export project in Texas.

Sempra’s ECA LNG export project starts pre-commissioning activities

Sempra's Energia Costa Azul LNG export terminal in Mexico is ready to start pre-commissioning activities, according to Karen Sedgwick, Sempra’s executive VP and CFO.