Finland-Estonia gas pipeline to get capacity boost

Finland’s gas system and LNG terminal operator, Gasgrid, and Estonian gas system operator, Elering, have revealed plans to boost the capacity of the Balticconnector gas pipeline once repairs on the offshore section of the pipeline are complete.

The TSOs shut down the gas pipeline on October 8 due to a suspected leak and after that said that the earliest possible commissioning date of the Balticconnector would be at the beginning of April 2024.

Moreover, the National Bureau of Investigation, a unit of the Finnish Police, said in a statement on October 24 that a Hong Kong-flagged containership is believed to have caused the damage with its anchor.

The 77 kilometers bi-directional pipeline with a capacity of 2.6 bcm stretches from Paldiski, Estonia, to Inkoo, Finland where Gasgrid’s FSRU-based LNG import terminal is located.

Besides the offshore section, the pipeline includes land-based sections in Finland and Estonia.

Increased capacity from October 2024

Historically Balticconnector northbound capacity has ranged between 55-60 GWh/day in winter and 65 GWh/day in summer, according to Gasgrid.

In the direction from Finland to Estonia, a capacity of 78 GWh/day has been offered, approaching the maximum transportation capacity considering the pipeline’s diameter and design pressure, it said.

Gasgrid said enhancement of Latvia-Lithuania interconnection allows for higher gas volumes to be transported across the region.

The results of capacity calculations and transmission system operation modelling conducted collaboratively by the TSOs indicate that the technical capacity of the Balticconnector interconnection point can be increased, it said.

After the restoration of flows over the Balticconnector pipeline and once inspection and maintenance works in Estonian-Latvian system are executed, the base capacity will be increased in the Estonia-Finland direction to 70.5 GWh/day, according to Gasgrid.

“Considering the planned regional maintenance works foreseen in 2024, the increased capacity can be offered for the market starting from October 2024,” it said.

Eesti Gas, a unit of Estonian investment firm Infortar, recently said it will deliver three more LNG cargoes to Finland’s Inkoo FSRU-based terminal during the winter to help cover gas needs in Finland during the winter season while the Balticconnector pipeline is shut down.

This followed the winter capacity booking organized by Gasgrid’s LNG terminal unit for a total of six cargoes.

Finnish state-owned energy firm Gasum booked the three other winter slots for delivery to Excelerate Energy’s 150,900-cbm FSRU Exemplar, which serves Gasgrid’s import facility in Inkoo under a charter deal.

Most Popular

Atlantic LNG shipping rates, European prices down

Atlantic LNG freight shipping rates and European prices decreased this week compared to the week before.

Glenfarne becomes majority owner of Alaska LNG

US energy firm Glenfarne has signed definitive agreements with state-owned Alaska Gasline Development Corporation to become the majority owner of the giant Alaska LNG export project.

Petronas to supply LNG to PetroVietnam Gas

Malaysian energy giant Petronas will supply liquefied natural gas (LNG) to PetroVietnam Gas, a unit of state-owned PetroVietnam, next month. The two firms will also look into the possibility of signing long-term LNG contracts.

More News Like This

Eesti Gaas using gas storages in Poland and Germany for winter

LNG importer Eesti Gaas, a unit of Estonian investment firm Infortar, has started using underground gas storage facilities in...

Gasgrid: Inkoo FSRU capacity 50 percent booked in 2025

In July, Gasgrid's unit Floating LNG Terminal Finland offered in total of 22 terminal slots of 950 GWh each...

Finland’s Gasgrid offers Inkoo FSRU capacity for 2025

A unit of Finland’s Gasgrid is offering regasification capacity for 2025 at the FSRU-based LNG import terminal in Inkoo. According...

Gasgrid: Inkoo FSRU capacity 95 percent booked in 2024

Finland’s gas system and LNG terminal operator Gasgrid said companies have booked 95 percent of the offered regasification capacity...