Kosmos says BP’s Tortue FLNG project slightly delayed

The first phase of BP’s Greater Tortue Ahmeyim FLNG development offshore Mauritania and Senegal will be slightly delayed, according to project partner Kosmos Energy.

Dallas-based Kosmos said on Tuesday the project partners have received a revised forecast from the EPCIC contractor, TechnipFMC. The contractor said that COSCO Shipping’s Qidong yard would likely deliver the FPSO later than planned.

This is due to “labor shortages at the COSCO yard in China following a ramp up in activity at the shipyard as the pandemic recedes,” Kosmos said.

Kosmos said the partners expect this would delay the project for about three months, pushing the timing of first gas to the third quarter of 2023.

BP, as operator of the project, has informed partners that costs would probably increase due to the impacts of Covid-19, including the FPSO delay, cost inflation and scope growth, the firm said.

On the basis of the revised schedule, Kosmos currently expects the gross cost for the project to be about 15% higher, resulting in an estimated increase of Phase 1 costs to first gas net to Kosmos of around $100 million, coming primarily in 2023.

Moreover, Kosmos expects the FPSO sale and lease back transaction to close this quarter upon the finalization of the documentation between the governments and partners.

Following the closing of the transaction, the company will work to complete the refinancing of the National Oil Company loans, Kosmos said.

Second phase FID

In addition, the project partners continue to make progress on the second phase of the LNG project with a final investment decision targeted for late 2022, the firm said.

The Tortue/Ahmeyim gas field, located offshore on the border between Mauritania and Senegal, has about 15 trillion cubic feet of gas, according to BP.

The FPSO will process the gas, removing heavier hydrocarbon components, prior to delivering it to a floating LNG provider which will sit nearshore a hub.

Besides operator BP and Kosmos, the project includes national oil companies Petrosen and SMHPM.

Furthermore, Singapore’s Keppel shipyard is currently converting Golar’s Gimi FLNG for the project. BP and Golar agreed on a one-year delay for the unit last year due to the Covid-19 coronavirus pandemic.

The yard should deliver the FLNG in 2023.

Once deployed offshore Mauritania and Senegal, it would provide about 2.5 million tonnes of LNG per annum on average.

Most Popular

Glencore pens Chinese LNG supply deal

Switzerland-based energy trader Glencore has signed a long-term deal to supply liquefied natural gas (LNG) to a unit of China Suntien Green Energy.

Equinor seals long-term LNG SPA with Thailand’s PTT

Norwegian energy firm Equinor has signed a long-term LNG sales and purchase agreement with a unit of Thailand’s PTT.

Atlantic LNG rates continue to increase

Atlantic spot LNG shipping rates rose for the third week in a row, rising $5,250 week-on-week to $25,250 per day, according to Spark Commodities.

More News Like This

BP to sell Browse LNG stake to Osaka Gas

UK-based energy giant BP has agreed to sell a 5 percent stake in the planned Woodside-led Browse LNG project in Australia, which would deliver natural gas from the Calliance, Torosa, and Brecknock fields to the existing Karratha gas plant, to Japan's Osaka Gas.

BP, XRG secure license for Venezuela offshore gas field

UK-based energy giant BP, Adnoc's international investment unit XRG, and a unit of Qatar's UCC have secured a license to explore and develop the second phase of Venezuela's offshore Loran gas field.

BP to take full control of Trinidad gas project

UK-based energy giant BP has agreed to acquire Woodside’s 70 percent interest in the Calypso gas project in Trinidad and Tobago, increasing its stake to 100 percent and assuming operatorship.

BP to supply another spot LNG cargo to Pakistan

A unit of UK-based energy giant BP has submitted the lowest bid in a tender to supply Pakistan with one spot LNG shipment this week.