Mozambique LNG restart may take another year, TotalEnergies CEO says

TotalEnergies will not restart work on its $20 billion Mozambique LNG project until the civil population comes back to the Cabo Delgado province where the Afungi site is located, according to chief executive Patrick Pouyanne.

To remind, TotalEnergies declared force majeure on the giant LNG project in April last year following new attacks, and withdrew all personnel from the site.

After that, the firm said the project would be delayed for a least one year.

Pouyanne recently visited Mozambique and met with the country’s President Filipe Jacinto Nyusi to discuss the security situation in the area where the LNG plant is located and the restart of works.

“We will not build a plant in a country surrounded by soldiers”

The CEO told analysts during the company’s quarterly results call on Thursday that, “there have been some clear improvements on the ground.”

Pouyanne said that Mozambique in partnership with SADC managed to get back the security in some key areas around Palma, where the project is located, but they “do not control today Cabo Delgado” in full.

He said that TotalEnergies would only restart the project once they take back the control of the security but also once the civil population comes back in the villages and with “a normal life.”

“That will be the signal. We will not build a plant in a country where we’ll be surrounded by soldiers. It does not work like that,” he said.

“No pressure to exit out of force majeure”

Pouyanne said he has “no idea” when the company could start working on the project again.

“Maybe it will take a year, I don’t know. We’ll see, we observe,” he said.

“There is no pressure for us to exit out of force majeure. We know that when we will say, yes, we can come back, it will take 6 months really to start up again,” he said.

“But again, my priority, it’s a matter of sustainability of that and human rights. And so we’ll not relaunch the project as long as I see photos from refugee camps around the site,” he said.

TotalEnergies had previously planned to launch the project in 2024. Mozambique LNG includes the development of offshore gas fields in Mozambique’s Area 1 and a 12.8 mtpa liquefaction plant at the Afungi complex.

The project will also have a fleet of dedicated LNG carriers.

Besides TotalEnergies, other partners in the project are Japan’s Mitsui, Mozambique’s ENH, Thailand’s PTT, and Indian firms ONGC, Bharat Petroleum, and Oil India.

The project’s EPC contractor is CCS JV, a venture between Saipem, McDermott, and Chiyoda.

Most Popular

NextDecade progresses commissioning of first Rio Grande LNG train

US LNG developer NextDecade is moving forward with commissioning activities at the first liquefaction train of its Rio Grande LNG terminal in Texas, and it continues to expect first gas into the LNG facility before year-end 2026.

Inpex wraps up Abadi LNG FEED work

Japan's Inpex has completed the front-end engineering design (FEED) work for the Abadi LNG project in Indonesia, the company confirmed to LNG Prime on Wednesday.

SEFE, Trafigura seal five-year gas supply deal

German gas and LNG importer Securing Energy for Europe (SEFE) has signed a new five-year gas supply contract with commodity trader Trafigura.

More News Like This

TotalEnergies reports lower LNG sales, higher LNG profit

French energy giant TotalEnergies reported lower LNG sales in the third quarter of this year compared to the same quarter in 2025, while its integrated LNG business logged higher adjusted net operating income due to higher prices.

TotalEnergies expects Q3 LNG results to rise sharply

French energy giant TotalEnergies, one of the world’s largest LNG players, expects its integrated LNG results to rise sharply in the third quarter compared to the prior quarter, driven by higher prices.

TotalEnergies plans second Mozambique LNG phase

French energy giant TotalEnergies plans to expand its Mozambique LNG project, currently under construction in Cabo Delgado province, with a second phase, according to management.