ADCC pipeline starts delivering gas to Cheniere’s Corpus Christi LNG plant

The ADCC pipeline has started delivering natural gas to Cheniere’s Corpus Christi LNG export terminal in Texas.

According to a joint statement issued on Friday, the pipeline entered commercial service on July 1, and is capable of providing about 1.7 Billion cubic feet per day (Bcf/d) of natural gas transportation capacity to the Corpus Christi facility from markets on Whistler Pipeline’s Agua Dulce Header in South Texas.

The receipt points in Agua Dulce provide Cheniere direct access to Permian and Eagle Ford volumes in addition to volumes sourced along the Gulf Coast, the statement said.

The ADCC Pipeline further enhances the natural gas infrastructure in Texas and creates an additional demand point for Permian gas.

This infrastructure is expected to help reduce flared volumes in the Permian Basin and further support US LNG exports to global markets, the statement said.

The ADCC pipeline is a joint venture owned 70 percent by Whistler Pipeline, which is a joint venture between WhiteWater (50.6 percent), MPLX (30.4 percent, and Enbridge (19 percent), and 30 percent by a wholly-owned subsidiary of Cheniere.

Back in September 2022, US LNG exporting giant Cheniere signed a deal with Whistler Pipeline to expand the latter’s existing pipeline in order to deliver natural gas from the Permian Basin to the Corpus Christi LNG export plant.

The consortium operates the 724 kilometers long pipeline that transports natural gas from the Waha Header in the Permian Basin to Agua Dulce, Texas, while the new pipeline is about 65 kilometers long.

Corpus Christi LNG expansion

Cheniere’s Corpus Christi liquefaction plant now has three operational trains with each having a capacity of about 5 mtpa.

In June 2022, Cheniere took a final investment decision to build the Corpus Christi Stage 3 expansion project worth about $8 billion.

This project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa, and the project was 60.4 percent complete as of May this year, according to the May construction report filed with the US FERC.

Cheniere expects to start producing LNG from the first midscale train this year.

Besides this expansion, Cheniere plans to take a final investment decision in 2025 to build two more midscale trains at its Corpus Christi LNG plant.

The CCL midscale trains 8 and 9 project would include two trains, nearly identical in design to trains 1-7 and each capable of producing up to 1.64 mtpa of LNG, on-site refrigerant storage, a 220,000-cbm LNG storage tank, a BOG compressor, and an increase in the authorized LNG loading rate.

According to a Cheniere presentation published on June 17, the project could have a capacity of about 5 mtpa when debottlenecking potential is included.

Most Popular

Venture Global seals new deals to support expansion of its power network

US LNG exporter Venture Global has entered into power and grid frame agreements with GE Vernova and Baker Hughes for up to 16 new, 720 MW power island units and associated power transformer equipment, supporting the continued expansion of its existing behind-the-meter, industrial power network that is not reliant on the grid.

Hanwha Ocean, Posco plan to build LNG carrier with high-manganese steel tanks

South Korean shipbuilder Hanwha Ocean and steel producer Posco plan to build a liquefied natural gas (LNG) carrier equipped with high-manganese steel cargo tanks.

Taiwan’s CPC makes progress with Alaska LNG deal

Taiwan’s CPC Corp is making progress on buying LNG and investing in the planned Glenfarne-led Alaska LNG project, according to Taiwan's economy ministry.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project 55.6 percent complete

US LNG exporter Cheniere continues to progress construction on its Corpus Christi Midscale Trains 8 and 9 project in Texas.

Cheniere, Petrobras seal long-term LNG SPA

US LNG exporter Cheniere has signed a long-term LNG sale and purchase agreement with Brazil’s state-owned energy firm Petrobras

US FERC issues final EIS for Cheniere’s Sabine Pass expansion project

The US Federal Energy Regulatory Commission (FERC) has released a final environmental impact statement for Cheniere’s planned Sabine Pass Stage 5 expansion project. The regulator confirmed that construction and operation of the LNG project would result in “some adverse environmental effects; however, effects would be reduced to less-than-significant levels.”

FERC issues draft EIS for Cheniere’s Corpus Christi Stage 4 project

The US Federal Energy Regulatory Commission (FERC) has released a draft environmental impact statement for Cheniere’s planned Corpus Christi Liquefaction Stage IV expansion project in Texas. The regulator concluded that construction and operation of the LNG project would result in “some adverse environmental effects; however, effects would be reduced to less-than-significant levels.”