Canada’s Pieridae still expects Goldboro LNG FID by end-June

Canada’s Pieridae Energy still expects to make a final investment decision on its Goldboro LNG export terminal in Nova Scotia by June 30, after postponing the decision last year.

The firm confirmed this in its quarterly report on Thursday.

“As we continue to make tangible progress with our Goldboro LNG project, ours is beginning to look like ‘the last one standing’ with others in North America either being delayed or canceled outright,” Pieridae’s chief executive Alfred Sorensen said in the report.

Pieridae aims to build a facility with two 5.2 mtpa trains that would employ about 3,500 workers during the peak construction phase. The project’s total costs could reach $10 billion.

The firm has a 20-year binding contract with German energy firm Uniper for all of the volumes from the first liquefaction train.

Depending on the FID, the firm plans to start commercial LNG deliveries to Uniper between August 31st, 2025 and February 28th, 2026, it previously said.

Bechtel to deliver price proposal by the end of May

Pieridae has also last year teamed up with Bechtel on Goldboro LNG after US engineer KBR backed out of signing the lump sum deal.

“We are working with them to define the lump sum turn-key cost by the agreed-upon deadline of the end of May 2021 to construct the Goldboro LNG facility,” Pieridae said in the quarterly report.

In addition, the firm said it has moved a number of contracts forward for tender to complete the extensive preparation work needed at the LNG site located at the Goldboro Industrial Park in Guysborough County.

Pieridae also plans to build a huge workforce lodge on or nearby the existing decommissioned Sable Island sour gas plant site.

The Nova Scotia Mi’kmaq and Black Diamond Group will construct and operate the lodge.

Moreover, Pieridae says it aims to make Goldboro LNG a net-zero emissions project by 2050.

Vancouver-based Navius Research provided research that “outlines pathways to achieve net-zero emissions,” the firm said.

- Advertisements -

Most Popular

South Korean yards built 500 LNG carriers for export in 30 years

South Korean yards have completed 500 liquefied natural gas (LNG) tankers for export since 1994, according to the Ministry...

MARAD: Delfin needs to submit amended application for FLNG project

The US Maritime Administration (MARAD) said that Delfin LNG needs to file an amended application for its floating LNG...

TotalEnergies takes FID on Marsa LNG bunkering project in Oman

French energy giant TotalEnergies has taken a final investment decision on the Marsa LNG bunkering project in Oman. Technip...

More News Like This

Woodside: largest compressor module arrives at Pluto Train 2 site

Australian LNG producer Woodside has received the largest compressor module from Indonesia at the Pluto Train 2 project site...

Work progresses on NextDecade’s Rio Grande LNG export plant in Texas

US LNG firm NextDecade is moving forward with construction work on the first phase of its Rio Grande LNG...

Tellurian expects to take FID on two Driftwood LNG plants in 2024

US LNG firm Tellurian said on Monday it expects to take a final investment decision in 2024 to build...

Woodside: first Pluto Train 2 modules installed

Australian LNG producer Woodside has received the first three modules from Indonesia at the Pluto Train 2 project site...